提升电力配网工程物资供应时效探索实践
2018-01-28崔立冲
崔立冲
【摘 要】近年来,河北公司煤改电、光伏扶贫等政府重点工程持续上马,大风、暴雨等自然灾害频发,同时雄安新区建设、业扩配套工程均对物资供应保障提出了新的更高要求。目前物资供应链管理存在供货周期过长、应急保障不强、运输管控缺失、单据传递和合同结算低效等问题。
【Abstract】In recent years, the key government projects of Hebei company, such as reforming coal to electricity and photovoltaic poverty alleviation have been continuously launched. Natural disasters such as gale and rainstorm occur frequently. The construction of the Xiong'an new area and the supporting projects for industrial expansion have put forward new and higher requirements for material supply protection. At present, the supply chain management of materials has many problems, such as long supply cycle, weak emergency support, lack of transportation control, inefficient delivery of documents and contract settlement.
【关键词】物资;供应;探索;实践
【Keywords】 material;supply; exploration; practice
【中图分类号】F252 【文献标志码】A 【文章编号】1673-1069(2018)11-0033-02
1 引言
随着人民生活水平提高,对供电质量的要求也逐渐提升。国家电网公司不断加强配电网建设,也对配网物资供应效率和设备质量均提出明确要求。 大气污染传输通道治理的“煤改电” 工程、精准扶贫的“光伏扶贫”工程等,政府对物资供应时效提出了更高的要求。部分地区缺少省级中心库支撑,配网物资供应链体系建设缺失重要一环,配网物资集中配送、应急保障能力严重不足,无法发挥统一存储、集中抽检、按需领用或配送的集约化运作优势。
2 借助大数据分析,智慧决策需求计划
电网企业配网物资主要通过协议库存物资采购方式实现,协议库存物资采购是在还没有开展可研、初设等前期工作作为支撑的一种采购方式,是需要对历史上迎峰度夏的重过载、农网升级改造、煤改电、光伏扶贫等不同类型项目下不同规格型号的物资消耗情况进行分析,结合未来一定时期投资情况,综合考虑各类项目投资规模,预测后期物资需求情况。以往物资需求计划预测,均依靠人工逐项对海量信息进行比对,从分析方法、计算策略、计算因素等方面难以做到多样化和颗粒度的精细化,不足以实现对后续结果预测的全面,准确。……