被动式营房施工进度综合评价研究
2018-09-19回月彤
回月彤


摘要:从环境的角度分析影响被动式营房施工进度的因素,建立被动式营房施工进度指标体系,以被动式营房活动持续时间为综合评价目标,确定预计工期,为被动式营房进度管理提供科学依据,提高计划管理与进度控制的科学水平,优化资源配置,提供工程建设效率。
Abstract: This paper analyzes the factors affecting the construction progress of passive barracks from the perspective of environment, establishes the passive barrack construction progress indicator system, takes the duration of passive barracks activity as the comprehensive evaluation target, determines the estimated construction period, to provide scientific basis for passive barracks schedule management, improve the scientific level of plan management and schedule control, optimize resource allocation, and provide engineering construction efficiency.
關键词:被动式营房;环境因素;施工进度;综合评价
Key words: passive barracks;environmental factors;construction progress;comprehensive evaluation
中图分类号:TU722 文献标识码:A 文章编号:1006-4311(2018)30-0011-03
0 引言
营房建设是官兵生活最基本的保障,被动式营房满足现代化营房建设的基本要求。被动式营房区别于传统营房,对技术和材料的使用有更高的标准,工序增多,工艺复杂,影响工程建设中的不确定因素增多,工程进度管理风险增高。营房在建设过程中除了要严把质量关,严控成本关以外,对进度管理的要求更为严格,分析影响工程施工进度的环境因素,防止进度计划产生过多的偏差,建立有效评价工程施工进度的体系,可以为被动式营房建设管理的提高效率,为编制精确可行的进度计划提供有效的保障[1]。
1 被动式营房建设施工进度的影响因素
被动式营房建设的影响因素存在多样化、复杂化的特点,地域性、季节性等因素导致了施工进度计划产生偏差的原因不径相同。从环境的角度分析,总体上主要分为五个因素:自然因素、社会因素、经济因素、技术因素和管理因素。
1.1 自然因素
在被动式营房施工过程中,各种自然因素对项目进度有着直接的影响。复杂的工程地质条件、不明的水文气象条件、地下埋藏文物的保护、处理、洪水、地震、台风等不可抗力等,都可对施工进度产生重大影响[2]。……