关于采煤工作面更改出煤系统设备安装技术探析与应用
2020-08-31郭军民
郭军民

摘要:随着煤炭行业的发展,井下地质条件越来越复杂,为了优化采煤工作面设计,提高出煤质量,新三矿通过变更出煤系统,更大限度的提高生产效率,实现安全生产。本文简单介绍了162316工作面随外推需求将出煤系统改至溜子道出煤眼,改出煤系统期间需拆除安装机电设备实践为例,归纳现场采取的有效措施,为煤矿企业提供了借鉴意义。
Abstract: With the development of the coal industry, underground geological conditions have become more and more complex. In order to optimize the design of coal mining face and improve the quality of coal production, the coal production system of the new No.3 Mine has been changed to improve production efficiency and achieve safe production. This article briefly introduces the change of the coal production system to hurry channel coal exit with the extrapolation need of 162316 working face. The practice of removing and installing electromechanical equipment during the coal production system is takes as an example. It summarizes the effective measures taken on site and provides a reference for coal mine enterprises.
关键词:更改出煤系统;设备安装;有效措施
Key words: to change coal production system;equipment installation;effective measures
中图分类号:TD407 文獻标识码:A 文章编号:1006-4311(2020)24-0159-02
1 工作面地质概况
162316工作面,井下位于北翼,北至F4断层;南至f1断层;工作面东、西两侧均为采空区,该工作面为北翼大巷煤柱块段。本工作面煤层走向N22°W,倾向NE,倾角平均为10°,煤层平均厚度3.4m。西南方向至东北部2煤与2上煤层间距逐渐变小,最小1.3m,最大5.0m,平均2.8m。本工作面南北夹与f1、F4断层之间,形成地垒式地质构造,工作面为单斜构造。工作面周围发育有4条已查明的正断层。
2 采煤工作面更改系统设备安装存在问题
2.1 工作面更改出煤系统基本情况
随着162316工作面外推,拆除第二部150溜子机头,将两部150溜子组合。改为162316出煤眼出煤后,需延长150溜子,在出煤眼铺设40溜子和150溜子各一部。(图1)
2.2 设备安装存在安全隐患
本工作面存在以下问题,一是顶板掉砟伤人;二是设备误动作伤人;三是人工搬抬设备不协调磕手碰脚伤人;四是大件起吊固定不牢滑脱伤人;五是溜子机头机尾翘起伤人,拆、接链时链断伤人。
3 安装设备技术策略
3.1 两部150溜子组合施工措施
①施工前一班,必须开空两部150溜子,并将溜子两侧活煤清理干净,施工前,将施工范围内的管线吊挂或盘好,严禁管线拖地绊人,确认无问题后,方可进行施工。……