千米深井安全高效施工技术

2017-07-08郭超贾振刚

价值工程 2017年21期
关键词:高效

郭超+贾振刚

摘要:本文针对深立井井筒施工面临的许多新的技术难题,开展深立井井筒安全高效快速施工关键技术研究,构建深立井井筒新的凿井施工工艺,科学优化与完善凿井设备布置和装备配套,形成深立井高效、安全施工的关键技术储备。对全面提升深立井井筒施工技术和加快井筒的施工速度意义重大。

Abstract: In this paper, in view of many new technical problems in the construction of deep well shafts, the key technologies of safe and efficient construction of deep well shafts are carried out, the new sinking construction technology of deep well shaft is built, the layout and supporting of drilling equipment are optimized, and the key technical reserves of efficient and safe construction of deep well shafts are formed. It is of great significance to improve the construction technology of deep well shaft and to speed up the construction speed of the wellbore.

关键词:井筒;凿井施工;高效

Key words: wellbore;sinking construction;efficient

中图分类号:TD608 文献标识码:A 文章编号:1006-4311(2017)21-0146-04

0 引言

立井井筒是矿井的咽喉要道,其施工速度决定着矿井建设的工期,其施工技术制约着我国深部资源开发和利用的发展。随着我国经济建设的迅猛发展,资源问题越来越成为制约科学、可持续发展的瓶颈问题。浅部矿山资源即将殆尽,因此迫切需要开发深部煤炭、金属及非金属矿产资源。目前,深部矿产资源的开发和开采已进入实施阶段,一批超千米矿山正在进行规划和建设。深立井井筒是我国今后一段时间矿山建设的主要任务。根据深立井井筒施工面临的许多新的技术难题,开展深立井井筒安全高效快速施工关键技术研究,构建深立井井筒新的凿井施工工艺,科学优化与完善凿井设备布置和装备配套,形成深立井高效、安全施工的关键技术储备。对全面提升深立井井筒施工技术和加快井筒的施工速度意义重大。

1 工程概况

主井工业场地与九龙矿工业场地联合布置,主井工业场地标高+117m。主井净直径7m,井深971.008m。表土段采用冻结法施工,冻结深度200m,双层钢筋混凝土复合井壁,支护厚度950mm/1000mm。……

登录APP查看全文

猜你喜欢

高效
让学习在复习课中真正发生
如何实现小学语文课堂教学的“高效”
浅谈交互式电子白板在中学英语课堂的有效应用
计算机网络技术对物流信息化的影响
对高校思政课教师暑期社会实践的探索与思考
如何实现小学语文课堂教学的高效化
农田水利工程高效节水灌溉发展思路初探
提高提问的有效性, 构筑高效的语文课堂
打造务实、创新、高效的语文课堂
高校三维动画课程教学方法研究