金庄矿综放工作面轨道铺设技术参数优化设计

2016-10-21田学春

价值工程 2016年9期
关键词:优化设计

田学春

摘要: 综放工作面轨道巷主要担负着运输综采支架等大型设备的重任,如果前期施工轨道铺设不合理,就会给后期安装提升运输综采设备带来安全隐患和整改难度。金庄矿3302综放工作面相比同条件下3207综放工作面,在轨道巷掘进过程中,提前对轨道铺设等优化设计,为后期综采设备实现顺利运搬打下基础,与之相比,取得较好的社会效益和经济效益。

Abstract: The fully mechanized caving face track lane is mainly used for transportation of fully mechanized mining support and other large equipment. If the early construction track laying is unreasonable, it will cause security risks and correction difficulty for later installation and lifting of fully mechanized mining equipment. Compared with 3207 fully mechanized caving face in Jinzhuang mine, 3302 fully mechanized caving face, under the same conditions, optimized the design of track laying in advance, which lays foundation for smooth transportation of equipment later and achieves good social and economic benefits.

關键词: 工作面;轨道巷;铺轨;优化;设计

Key words: working face;roadway;laying;optimization;design

中图分类号:TD823 文献标识码:A 文章编号:1006-4311(2016)09-0102-02

0 引言

综采工作面的安装主要考虑大型综采设备运输问题,对于轨道铺设质量等有较高要求。金庄矿3207综放工作面由于轨道铺设不理想,在安装过程中数次出现运输液压支架掉道问题,带来安全隐患。在相同条件下3302综放工作面掘进铺轨时,按照优化设计方案施工,提前考虑轨道运输铺设质量等满足安装要求,避免上述问题,践行了“安全可靠、技术可行、经济合理”设计三原则[1]效果良好。

1 工程概况

金庄矿年产煤量约60万吨,33采区3302综放工作面倾斜长度130m,走向长度460m,开采3煤平均5.6m厚,煤层赋存-500m~-600m,倾角0~18°,综采放顶煤工艺。工作面内分布落差0~10m数条断层,轨道巷沿3煤掘进,提前考虑后期运输综采设备问题,对巷道进行优化设计,掘进铺轨一次成形到位,安装期间没有出现歪架掉道问题。比相同条件下3207综放工作面安装效率提高三分之一。

2 轨道铺设技术参数优化设计

综采工作面运搬液压支架系统中,轨道铺设要达到平、稳、直,轨道曲线半径、轨道转弯处行进速度、轨面抬高值和轨距加宽值重点考虑。……