APP下载

大跨度框架顶进施工时铁路双线线路加固技术研究

2020-08-31陈俊超

价值工程 2020年24期
关键词:铁路施工

陈俊超

摘要:本文以下穿太焦铁路的框架顶进施工为例,详细说明了大跨度、双线铁路(线间距过小,线间无法设置支墩孔桩)的线路加固方法。并重点阐述了I100大工字钢、[3703]组合构件在线路加固中的应用,以期为此类困难条件下的线路加固提供参考。

Abstract: This article takes the frame jacking construction of the Taiyuan-Jiaozuo Railway as an example, and explains in detail the line reinforcement method of the large-span and double-track railway (the line spacing is too small, buttress hole piles cannot be set between the lines). It also focuses on the application of I100 large I-beam and [3703] composite members in line reinforcement, in order to provide reference for line reinforcement under such difficult conditions.

关键词:大跨度框架;双线铁路;线路加固;I100大工字钢;[3703]组合构件

Key words: long-span frame;double-track railway;line reinforcement;I100 large I-beam;[3703] composite member

中图分类号:U445.72                                    文献标识码:A                                  文章编号:1006-4311(2020)24-0147-03

0  引言

道路及涵洞等工程下穿铁路的施工建设通常采取预制后顶进法施工,为了维持铁路的正常运营,对铁路线路进行防护、加固是必不可少的,但随着顶进框架等构筑物跨度日趋增大,且施工环境也是复杂多变,线路加固及防护的技术难度也是越来越大。本文以下穿太焦双线铁路大跨度的框架顶进施工为例,总结了在复杂及困难的施工条件下,下穿双线铁路大跨度框架顶进时的线路加固方法,以期探索、研究出更为安全可靠、技术可行的线路加固而方案。

1  工程概况及技术难点

长治市黑臭水体治理工程(穿太焦铁路工程)及涉铁地段河道整治工程位于石子河与太焦铁路交叉处。新建北侧人行步道及污水涵与太焦铁路交叉处里程为K241+907.18,南侧人行步道及污水涵与太焦铁路交叉里程为K242+038.1、河道扩孔涵与太焦铁路交叉处里程为K242+024.2,3座箱涵与太焦铁路交叉角度均为90°,采用线路架空顶进法施工,顶进方向为自东向西。其中南岸新建污水涵与南岸新建河道扩孔涵为紧邻设计,采取一次同时顶进法施工。……

登录APP查看全文

猜你喜欢

铁路施工
铁路是怎么发明的
后浇带施工技术在房建施工中的践行探索
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
沿着中老铁路一路向南
铁路通信线路维护体制改革探索与实践
无人机在铁路工程建设中的应用与思考
土木工程施工实习的探讨与实践
GSM-R在铁路通信中的应用
扶贫村里施工忙