浅谈超高压线下城市轨道交通现浇梁施工工艺研究

2018-02-06王波张立军朱荀

中小企业管理与科技·下旬刊 2017年12期

王波+张立军+朱荀

【摘 要】现浇桥梁在城市轨道交通建设工程中的应用已越来越广泛,但桥梁周围时常会遇到超高压线路障碍,且不能按照常规工艺施工,无疑增加了施工难度及安全风险。为了解决上述难题,须对其现浇梁正常施工工艺进行深入研究,研究出一套适合在超高压下现浇梁施工的特殊工藝,并达到工艺的安全性、实用性、可靠性。

【Abstract】Cast-in-place bridge in urban rail transit construction project has become more and more widely, but there are frequent high voltage line barriers around the bridge, and it can not construct according to the conventional process of construction, undoubtedly increased the construction difficulty and safety risk. In order to solve above problem, we must research the normal construction technology in-depth, develop a set of special technology suitable for the construction of cast-in-place girder under super high pressure, and achieve the safety, practicability and reliability of the process.

【关键词】现浇桥梁;超高压线;特殊工艺

【Keywords】cast-in-place bridge; ultra-high voltage line; special process

【中图分类号】U445 【文献标志码】A 【文章编号】1673-1069(2017)12-0190-04

1工程概况

1.1 工程基本概况

武汉市轨道交通21号线工程途经武汉市江岸、黄陂和新洲三个区,两端均预留延伸条件,一期工程从江岸区后湖大道至新洲区金台,线路全长33.7km,共设车站16座。本标为三标段,均为高架段,起始于军民村站(不含)—武生站高架,经武生站、武生站—平江路站、平江路站、平江路站—阳逻开发区站、阳逻开发区站、阳逻开发区站—施岗站(不含)、施岗站(不含)—金台站,止于金台站,本标段同时还包括倒水河车辆段出入线区间、倒水河车辆段及施岗主变电站,共4站6区间及车辆段1座,主变电站1座,正线全长11.178km(不含倒水河车辆段的长度)。本标段共有简支箱梁250孔,连续梁26联。

1.2 工程地质

地质主要为人工填土、淤泥质粉质粘土、泥质砂岩及粉细砂岩。

1.3 工程水文

①地表水

长河为常年性地表径流,地表水体水量受季节性降水影响显著,夏季一般水量较丰沛。

②地下水的类型、埋藏情况及其变化特征

地下水的主要类型为第四系孔隙潜水和基岩裂隙水。……