基于贝叶斯网络的施工项目进度计划动态更新方法
2017-12-01邓东磊胡颖
邓东磊+胡颖

摘要: 项目的工序间存在着普遍的相依性,在项目的进度管理中,合理考虑工时之间的相依性,有利于更加准确地预测和评估工期风险,从而更有效地控制工程进度。本文建立了一个基于贝叶斯网络的进度计划动态更新模型,度量工程进度网络中工序持续时间的相依随机性,并进行进度计划的动态更新,模型用贝叶斯网络表示工序间的相依关系,由专家估计工序持续时间的边缘分布及工序间协调系数,然后确定贝叶斯网络中的条件概率和分布,从而确定各工序持续时间的条件分布和总工期的分布。算例表明该模型能有效预测和控制工时的不确定性,有利于降低工程进度风险。
Abstract: There is the universal dependence between the project processes. In the project schedule management, considering the dependence between time reasonably, is conducive to predicting and assessing the schedule risk more accurately, so as to effectively control the progress of the project. This paper establishes an dynamic updating model of the schedule based on Bayesian network, which is used to measure the dependent random of the process duration in the project progress network, and dynamically update the schedule. The model uses Bayesian network to represent dependence between processes. The marginal distribution of process duration and the coordination coefficient between processes are estimated by experts, and then the conditional probability and distribution in the Bayesian network are determined, so as to determine the conditional distribution of each process duration and total duration. The example shows that the model can effectively predict and control the uncertainty of the working hours, which is conductive to reducing the project risk.
關键词: 项目进度管理;进度计划更新;相依随机变量;贝叶斯网络
Key words: project scheduling;schedule updating;dependent random variable;Bayesian Network
中图分类号:TU17;F426 文献标识码:A 文章编号:1006-4311(2017)33-0045-04
0 引言
在项目管理实践中,不同工序的工时变量之间存在普遍的相依性,且这种相依性受到诸多因素的影响。在实际的项目进度管理中,掌握各个工时变量之间的相依性意义重大,它能够将工期计划中的不确定性充分估计出来,提高了预测及评估工期风险的准确度,有利于施工项目工程的进度控制[1]。
国外很多学者都会项目进度网络中工时的线性相关性具有浓厚的兴趣,开展了较为深入的研究,建立的模型基本可归为三类,分别是仿真模型、解析模型、专家系统模型。Ringer[2]最早在PERT网络中考虑工时间的相关性,他提出了一个基于图论约简算法的解析模型;……