风电超高混凝土塔筒体内预应力施工及监测技术研究
2021-09-28黄汉斌简铃方王波王雄彪彭渝舒王晓琳
黄汉斌 简铃方 王波 王雄彪 彭渝舒 王晓琳
DOI:10.16660/j.cnki.1674-098X.2107-5640-0187
摘 要:当前,风电塔筒主要采用钢塔筒或者钢混组合塔筒结构形式,超高型混凝土塔筒作为一种新的结构形式,由于其能够有效地提升整机发电量、降低维护成本,得到快速的发展及推广应用。本文结合新疆哈密某风电场工程项目,对超高混凝土塔筒体体内预应力施工及监测技术应用进行了研究,可为类似结构提供参考。
关键词:高层建筑 框架结构 无缝钢管 管棚加固
中图分类号:TU3 文献标识码:A 文章编号:1674-098X(2021)06(b)-0004-03
Research on prestressed construction and monitoring technology in Ultra-high concrete tower of wind power
HUANG Hanbin JIAN Lingfang WANG Bo WANG Xiongbiao PENG Yushu WANG Xiaolin
(Liuzhou OVM Machinery Co., Ltd., Liuzhou, Guangxi Zhuang Autonomous Region, 545006 China)
Abstract: At present, wind power tower drum mainly adopts the structure form of steel tower drum or steel-concrete composite tower drum. As a new structure form, ultra-high concrete tower drum is rapidly developed and applied because it can effectively improve the power generation of the whole machine and reduce the maintenance cost. Combined with a wind power plant project in Hami, Xinjiang, this paper studies the application of prestressed construction and monitoring technology in the body of ultra-high concrete tower cylinder, which can provide reference for similar structures.
Key Words: Wind power; Ultra-high concrete tower; Prestressed construction; Monitoring technology
随着风力发电技术的不断突破,风能作为一种成熟利用的可再生清洁能源,得到了国家的大力发展推广。风力塔筒采用超高型混凝土塔筒新型结构可提高整机发电量、降低建设维护成本。塔筒结构在承受外荷载之前,对塔筒内部预应力束进行张拉,以提升塔筒结构的整体刚度,提高整体抗风荷载能力,改善风机组运营过程塔筒结构的耐疲劳性[1]。本文结合实际工程研究120m超高混凝土塔筒的预应力施工工法及监测技术,为类似结构设计与应用提供参考和借鉴。
1 项目工程概括
新疆哈密某风电厂C共采用100台混凝土塔筒,塔筒行间距约260m,排间距约1.6km。混凝土塔筒高120m,共30段,每段高約4m,使用体内预应力连接。单个塔共40束体内预应力索,每束由4根φ15.2钢绞线组成,采用φ60金属波纹管成孔。监测的每个节段预制时预埋安装预应力索索力监测磁通量传感器,单个塔筒安装20台监测点。
2 混凝土塔筒体内预应力方案设计……p>