白狮水库工程施工导流设计研究
2021-07-22董泽刚
董泽刚


摘 要:白狮水库工程初步设计阶段,详细地论证分析了导流时段、流量、导截流方式以及导流建筑物结构等施工导流关键技术问题,提出了合理的施工导流方案。工程采用围堰一次拦断河床、左岸导流洞过流的导流设计方案,既能满足工程施工现场导截流和安全度汛的需求,又可以使水库大坝连续快速施工,为安全、可靠、节能、经济且高效的施工奠定基础,效果良好。
关键词:白狮水库;水文地质;导流时段;围堰
中图分类号:TV551.1 文献标识码:A 文章编号:1003-5168(2021)08-0069-03
Study on the Construction Diversion for Baishi Reservoir Project
DONG Zegang
(Guizhou New Zhongshui Engineering Co.,Ltd., Guiyang Guizhou 550002)
Abstract: The key technical problems of construction diversion such as diversion period, flow rate, diversion and closure mode, diversion structure have been discussed in detail in the preliminary study stage, and a reasonable construction diversion scheme has been put forward. The cofferdam blocking all the river way in once and left tunnel flow river diversion scheme have been adopted, and this diversion scheme is feasible, which not only meet the safe flood-passing requirements but also could achieve the safe continuous, rapid, and energy-efficient economy character for the reservoir construction.
Keywords: Baishi reservoir; hydrogeology; diversion period; cofferdam
1 工程概况
白狮水库位于贵州省遵义市正安县流渡镇的白花村境内,所在河流流渡河为芙蓉江一级右支流,属长江流域乌江水系。大坝枢纽区距正安县55 km,距贵阳市265 km,距大坝下游右岸约2.0 km的新桥村附近有X328县级公路通过,对外交通条件较好。工程任务是解决正安县滨江新区(现芙蓉江镇)、流渡镇区以及土坪镇区周边农村人畜用水及农田灌溉用水问题,年供水量1.396×107 m3。水库规模为中型,属Ⅲ等工程。工程挡水、泄水及取水建筑物等主要建筑物为3级,次要建筑物为4级,临时建筑物为5级。枢坝区主体工程(含导流工程)土石方明挖1.731×105 m3,石方洞挖1.1×104 m3,混凝土1.672×105 m3,钢筋制安1 709 t,固结灌浆总进尺1.1×104 m,回填灌浆0.3×104 m2,帷幕灌浆总进尺1.11×104 m,金属结构安装101 t,工程总工期30个月。
2 工程水文地质条件
白狮水库库区干支流汇口以上干流河段控制流域面积为17.3 km2,主河道河长8.03 km,河床平均比降35.6‰;支流河段控制流域面积为21.4 km2,主河道河长7.28 km,河床平均比降39.9‰。水库所属流域属典型的山区雨源性河流,径流主要由降水补给,径流特性与降水特性基本一致[1-2]。……