乌东德水电站超大型地下埋管内支撑优化设计及应用
2021-01-04焦雄邓朝
焦雄 邓朝



摘要:乌东德水电站引水压力钢管具有直径大、钢板厚、制作及安装质量要求高等特点。为了保证其安装质量和施工安全,达到节省施工资源投入,加快施工进度的目的。采用有限元软件,对压力钢管管节不同吊点、外包混凝土浇筑进行变形分析,结果显示压力钢管优化内支撑的施工方案是可行的,该方案在乌东德水电站超大型地下埋管施工中得到了成功应用,是水利水电工程压力钢管安装技术的一次大胆创新,值得类似工程借鉴和参考。
关键词:乌东德水电站 地下埋管 内支撑 优化设计 应用
Optimization Design and Application of Super Large Underground Buried Pipes Support in Wudongde Hydropower Station
JIAO Xiong1 DENG Zhao2
(1.Hanjiang-to-Weihe River Valley Water Diversion Project Construction Co., Ltd., Xi’an, Shaanxi Province, 710010 China; 2.China Three Gorges Construction Engineering (Group) Co., Ltd., Sichuan Province, 610094 China)
Abstract: The penstock pipe joints of Wudongde Hydropower Station has the characteristics of large diameter, thick steel plate and high requirements for manufacturing and installation quality. In order to ensure the installation quality and construction safety, achieve the purpose of saving construction resources and speeding up construction progress, the finite element software is used to analyze the deformation of penstock pipe joints at different lifting points and wrapped concrete pouring.The results show that the construction scheme of optimized internal support of penstock is feasible, the scheme has been successfully applied in the construction of super large underground buried pipe of Wudongde Hydropower Station, pressure pipe installation technology of water resources and hydropower engineering of a bold innovation, worthy reference in similar engineerings.
Key Words: Wudongde Hydropower Station; Underground buried pipes; Inner support; Optimization design; Application
1概述
烏东德水电站为地下电站,左右岸地下电站各安装6台850MW水轮机组。引水隧洞采用一洞一机布置型式,平行布置。压力钢管布置在下平段,自灌浆帷幕处起始,灌浆帷幕下游设排水设施。钢管经下平段、锥管段、连接段至水轮机蜗壳端口[1]。左岸1#~6#机压力钢管直径Φ13.5m,经锥管段渐缩为Φ11.5m,由连接段与蜗壳进口端连接,6条压力钢管长度均为55.2m。右岸7#~12#机压力钢管直径Φ12.5m,经锥管段渐缩为Φ11.5m,由连接段与蜗壳进口端连接。7#机灌浆帷幕布置在下弯段部位,8#~12#机灌浆帷幕布置在下平段部位,7#机组引水压力钢管长为57.734m,8#~12#机组引水压力钢管长均为55.2m。12条压力钢管总长664.934m,总重量约为13227.316t[2]。
压力钢管采用800MPa级高强钢板制造,经计算,钢管壁厚为56~60mm(含锈蚀厚度)。钢管外布置加劲环,加劲环断面为矩形,间距2~3m,材质为Q345C,壁厚为34mm。
设计水位975m,水轮机安装高程为803m,单机引用流量700余m3/s,经调保计算,压力钢管的设计压力H(包括水锤升压值)为245.5m,HD值为3069m2,属于超大型地下埋管。……