浅谈桐子林水电站围堰高喷防渗墙施工技术措施
2020-06-08李姗姗
李姗姗


Discussion on the High-Jet Impervious Wall Construction Technology of Cofferdam in Tongzilin Hydropower Station
LI Shan-shan
(Chengdu Hydroelectricity Construction Engineering Co. Ltd. of Sinohydro Bureau No.7 Company, Chengdu 611130, China)
【摘 要】论文通过对大块石、孤石含量较高,细颗粒流失严重的土石围堰的高喷防渗墙施工技术进行阐述,总结了有关参数和施工工艺以及技术措施。
【Abstract】This paper expounds the construction technology of high-jet impervious wall of rock cofferdam with high content of large stone and solitary stone and serious loss of fine particles, and summarizes the relevant parameters, construction technology and technical measures.
【關键词】围堰 ;高喷防渗墙;施工技术
【Keywords】cofferdam; high-jet impervious wall; construction technology
【中图分类号】TU74 【文献标志码】A 【文章编号】1673-1069(2020)03-0173-03
1 桐子林水电站围堰概述
桐子林水电站一期土石围堰,堰顶宽12m,堰顶高程为994m,枯期围堰堰顶轴线总长1056.68m,最大堰高约16m,堰体分为砂砾石区和石渣堆筑区。一期围堰防渗采用高喷,深度一般在40.0m以内,局部最深为51.0m,布置于(围)
0-441.104~(围)0+615.574,高喷防渗墙轴线布置于围堰轴线内侧3.0m。枯期围堰典型剖面图如图1所示。
1.1 工程地质及水文
围堰基础置于河床覆盖层上,覆盖层厚3~38m,主要为砂卵砾石层、粉砂质粘土层,基岩为晋宁期混合岩,以Ⅳ级岩体为主,局部强风化Ⅴ级岩体[1]。
桐子林坝址枯水期(12月至翌年4月)平均流量为612 m3/s,每年11月起开始稳定退水,到翌年3月中下旬达最小值,枯水期水量年际变化以11、12月为最大,3月最小。历年3月平均流量最大为593m3/s(1966年),最小为422m3/s(1984年);4月起河道水量明显增加,月平均流量的最大值可达937m3/s(1992年),年际变化也相应变大。
1.2 围堰填筑情况
围堰填筑高度在原始河床上加高6~16m,该围堰堆筑大块石、孤石含量较高,粒径超过30cm以上的填筑石料含量较大,由于填筑高差大河床水流流速高,造成在水下部位的填筑过程中细颗粒及土料随水流流失较多,致使水下部位的填筑架空概率极高,这加大了高喷施工技术难度和质量风险[2]。
2 高压旋喷防渗墙施工
2.1 工程设计……p>