某引水工程施工支洞软岩变形控制工程实例
2020-05-21毕桉靖李春雁
毕桉靖 李春雁



摘 要:某引水工程施工支洞软岩洞段开挖施工中,出现不同程度中等及轻微变形,根据围岩变形监测数据,动态调整初期支护方案、适时进行二衬施工,最终将变形量控制在1cm~2cm,控制效果良好,对后续主洞施工及其他工程具有借鉴意义。
关键词:软岩;变形控制;监测;钢支撑
中图分类号:U455 文献标志码:A 文章编号:2095-2945(2020)15-0139-02
Abstract: During the excavation of the soft rock section of the branch tunnel of a water diversion project, different degrees of moderate and slight deformation occurred. According to the surrounding rock deformation monitoring data, the initial support scheme was dynamically adjusted and the second lining construction was carried out timely. Finally, the deformation is controlled at 1~2cm, and the control effect is good, which can be used as a reference for the follow-up main tunnel construction and other projects.
Keywords: soft rock; deformation control; monitoring; steel support
1 工程概述
某引水工程施工支洞长660m,支洞倾角23.4°,为斜井支洞,采用钻爆法施工、四线双车道有轨运输。支洞断面为圆拱直墙型,断面尺寸6.5m×6.0m(宽×高),采用50cm厚C25钢筋混凝土衬砌。支洞断面布置见图1:
本支洞自进口0+000m至0+100m桩号处,洞身埋深约7~110m,围岩物质成分以D1l弱风化钙质砂岩夹强风化炭质泥岩、泥灰岩为主,饱和抗压强度Rb=8~15MPa,局部发育泥化夹层,呈碎裂结构;全洞段岩体处于地下水位以下,洞顶及洞壁有面状滴水,局部有线状水流,洞顶及洞壁稳定性差,综合评判整体为Ⅴ类围岩,属特殊不良地质软岩洞段[1]。
该洞段原初期支护方案如下:超前小导管L=4.5m,φ42@30cm+钢支撑I20a型@60cm+纵向Φ25钢筋@100cm+挂网喷C20混凝土厚20cm+L=4.5m、Φ25系统中空注浆锚杆2.0×0.6m+工字钢底脚及起拱处每侧各2根Φ25、L=4.5m普通砂浆锁脚锚杆,断面见图2。
2 变形情况
施工支洞软岩段开挖过程中,现场按间隔约5m布置了安全监测断面进行围岩收敛监测,各断面监测频次为埋设后一周以内监测2次/天,一周后监测1次/天,待变形基本稳定后监测频次为3天一次。本施工支洞开挖至0+060m桩号时,根据0+025m~0+055m段变形监测成果,显示该洞段存在中等及轻微变形问题,各监测断面变形主要发生在开挖初支后的10日内,之后趋于收敛。……