双河口水库大坝施工组织设计
2019-10-21冷继菊
冷继菊
摘 要:结合双河口水库工程水文、地形、地质条件及工程主体建筑物特性等方面,本文采用合理的施工导流方式和主体施工方案。同时,从施工导流、主体工程施工、施工交通运输及施工总进度等方面,介绍工程施工组织设计的主要思路和成果。
关键词:施工组织;施工导流;双河口水库
中图分类号:TV64;TV512文献标识码:A文章编号:1003-5168(2019)29-0091-02
Dam Construction Design of Shuanghekou Reservoir
LENG Jiju
(Guizhou Zhongshui Construction Management Co., Ltd.,Guiyang Guizhou 550000)
Abstract: Combined with the hydrology, topography, geological conditions and characteristics of the main building of Shuanghekou Reservoir, this paper adopted reasonable construction diversion method and main construction scheme. At the same time, from the aspects of construction diversion, main construction, construction, transportation and construction progress, the main ideas and achievements of engineering construction organization design were introduced.
Keywords: construction organization;construction diversion;Shuanghekou Reservoir
双河口水库工程位于铜仁市思南县瓮溪镇上坝村境内,建坝河流属于长江流域乌江水系黑滩河二级支流。坝址位于上坝冲沟中游河段,坝址以上集水面积1.8km2。工程距瓮溪镇18km,距思南县城89km。工程以解决下游涉及灌面的灌溉用水为主,同时考虑解决邻近乡村生活用水。工程包括枢纽建筑物、输水管路两部分,为Ⅳ等小(1)型工程。
1 施工导流
双河口水库工程为Ⅳ等,工程规模属小(1)型,枢纽主要建筑物大坝、溢洪道、取水兼放空底孔、引洪沟等建筑物为4级建筑物。根据《水利水电工程施工组织设计规范》(SL 303—2017)规定,确定相应的导流建筑物级别为5级,枯期导流的挡水、泄水临时建筑物按5年一遇洪水標准(P=20%)进行设计,汛期导流标准按10年一遇洪水标准(P=10%)进行设计。导流时段选取为10月至次年3月,相应的导流设计流量Q=4.32m3/s,坝体施工临时度汛标准为10年一遇(P=10%)洪水,相应的设计流量Q10%=23.9m3/s。
1.1 导流方式
双河口水库工程导流方式比选如下。根据现场地形地质情况,建坝河段河床较窄,但两岸边坡较缓,比较适合采用分期导流方式;施工导流设计流量小,坝体为C15埋石混凝土重力坝,坝体抗风险能力较高,施工期如果发生超标准洪水,可预留缺口过流,洪峰消退后即可恢复施工,比较适合采用导流涵管导流方式;再者,采取涵管导流方式较为经济[1]。……