某吹砂回填场地地基预处理方案浅析
2019-08-13占三军马锋王辉
占三军 马锋 王辉

摘 要:吹砂回填场地土体多为饱和性的砂土,地质条件差,多为液化。该文以孟加拉国某电厂工程为实例,对吹砂回填场地地基预处理的几种方案进行浅析,并进行相关的技术经济比较,从而得到较为合理的方案。希望该文的分析结果能为吹砂回填场地地基预处理提供一定的指导作用。
关键词:吹砂回填场地 地基预处理 水泥土搅拌桩 振冲碎石桩 强夯法 真空动力固结法
中图分类号:TU472 文献标识码:A 文章编号:1672-3791(2019)06(a)-0057-02
Abstract: The soil in the sand-blowing backfill site is mostly saturated sand with poor geological conditions and mostly liquefaction. This paper takes a power plant project in Bangladesh as an example to analyze several schemes for ground pretreatment of sand-blowing backfill site. And take relevant technical and economic comparison, obtaining a more reasonable scheme. It is hoped that the analysis results of this paper can provide a certain guiding role for ground pretreatment of sand-blowing backfill site.
Key Words: Sand-Blowing Backfill Site; Ground Pretreatment; Ground Treatment cement deep mixed columns; Vibro-Replacement Stone Columns; Dynamic Compaction; Vacuum Dynamic Consolidation
1 工程概况及地质情况
该工程位于孟加拉共和国达卡市加济布尔,距达卡市区约21km,站址北侧约150m是Bongshai河流。厂区西侧为已建电厂,东侧为居民区,南侧为农田,北侧为变电站,厂区内现为荒地,分布有杂草及灌木。厂区在回填之前是一片沼泽地,雨季的时候全部淹没,旱季时才会部分露出水面。
场地在吹砂回填后,土质分布如下。
(1)冲填土,全场遍布,松散,具高压缩性,吹填时间短(1个月),不能作为建筑物天然地基持力层,需对其进行处理。
(2)粉质黏土夹粉土,大部分地段分布,层顶埋深4.00~6.00m,可塑,具中等压缩性,fak=120kPa,承载力一般,但层厚分布布均匀,不宜作为建筑物天然地基持力层。
(3)粉质黏土夹粉土(Q4al+pl),全场分布,软塑,层顶埋深4.50~10.50m,具高压缩性,fak=70kPa,承载力较低,不可作为建筑物天然地基持力层。
(4)粉质黏土、粉土互层,全场分布,层顶埋深6.00~20.00m,可塑,具中等压缩性,fak=150kPa,承载力一般。埋深浅处,可作为建筑物天然地基持力层,埋深深处,可作为建筑物桩端持力层。
(5)粉细砂夹粉土,全场分布,层顶埋深10.00~30.00m,中密,具低压缩性,fak=210kPa,承载力较高,埋藏较深,可作为桩端持力层。……