无内支撑两墙合一逆作法在深基坑施工中的应用

2018-09-05曹国安

曹国安

【摘 要】本研究以中铁上海局承建的上海白龙港污水处理厂扩建二期工程W2.3标为例,着重介绍了大型污水泵站圆形地连墙、无内支撑逆作内衬施工技术、基坑监控量测、污水泵站超长内衬防水技术,以为保障无内支撑两墙合一逆作法的施工质量提供借鉴和参考。

【Abstract】This study takes the W2.3 section of the second phase of the extension project of Shanghai Bailong port sewage treatment plant built by the CREC Shanghai Group as an example, it emphatically introduces the round connecting wall of large sewage pumping station, construction technology of inner lining without internal support, foundation pit monitoring measurement, and the waterproof technology of super long liner in sewage pumping station, so as to provide reference for ensuring the construction quality of the reversed construction method of dual-purpose diaphragm wall without internal support .

【关键词】逆作法;内支撑;深基坑

【Keywords】reversed construction method; internal support; deep foundation pit

【中图分类号】TV551.4 【文献标志码】A 【文章编号】1673-1069(2018)05-0134-02

1 引言

近年来,地下空间作为一种十分宝贵的不可再生资源不断受到关注和重视。无内支撑两墙合一逆作法在深基坑应用中具有诸多优势。与此同时,通过对相关文献的检索,发现目前国内外在环保领域采用无内支撑两墙合一形成圆筒形受力结构,但在对污水泵站内衬施工中还没有采用逆作法[1]。

2 工程概况

2.1 基本情况

上海白龙港污水处理厂扩建二期工程W2.3标项目,位于上海浦东新区合庆镇白龙港污水厂南侧。污水泵站,靠近长江口,地下水位埋深0.~1.5m,土层基本特征为杂填土、冲填土以及灰色淤泥质粉质粘土。

2.2 地下连续墙结构情况

水泵站地下连续墙是一个圆形,其内直径为60.7m,槽段有27幅。其中,12幅槽段是一个2边槽段,宽度为5.67m,偏角为5°13′03″。另外,15幅墙槽段,幅宽8.84m,厚度0.8m,最大幅长42m,钢筋笼最大起吊重量为42t,偏角为5°13′03″。

3 无内支撑两墙合一施工工序简介

施工工序主要依据以下工序进行:①污水泵站地下连续墙→②泵站基地加固→③坑内降水→④泵站顶部锁口梁及第一次内衬逆作→⑤监控量测布设及砼等强(100%)→⑥泵房第二次内衬逆作及砼等强(80%)→⑦泵站第三次内衬逆作及砼等强(80%)→⑧泵站第四次内衬逆作及砼等强(100%)→⑨泵站第五次内衬逆作及底板砼施工。……