地形复杂潮湿山区薄壁空心高墩翻模施工技术

2018-07-18靳长峰

价值工程 2018年16期
关键词:混凝土施工

靳长峰

摘要: 结合摆捞河大桥薄壁空心高墩的施工,介绍了薄壁空心高墩的翻模施工方法,从施工方案选择、翻模施工介绍、施工技术、质量控制等方面提出了具体的措施,利用翻模施工法施工薄壁空心墩,具有安全,施工速度快,节省投资等优点,可供类似工程借鉴。

Abstract: Combined with the construction of thin-walled hollow piers of the Bailao River Bridge, this paper introduces the construction method of turnover forms thin hollow piers, and puts forward specific measures from the aspects of construction scheme selection, construction introduction, construction technology and quality control. The construction of thin-walled hollow piers by the use of turnover forms construction method has the advantages of safety, quick construction, and investment saving, which can be used for reference for similar projects.

关键词: 地形复杂;潮湿;薄壁空心高墩;翻模;施工技术

Key words: complex terrain;humid;thin-walled hollow high pier;turnover form;construction technology

中图分类号:U445 文献标识码:A 文章编号:1006-4311(2018)16-0171-02

1 工程概况

凯里至羊甲高速公路摆捞河大桥7#~16#墩采用薄壁式空心墩,其中12#、13#墩为连续刚构主墩,墩高分别为72m、77m,11#、14#墩为连续刚构边墩,墩高分别为64m、77m,7#~10#及15#~16#为引桥墩身,最大墩高70m。12#、13#主墩为四柱式薄壁空心墩结构,截面尺寸为7m*2.5m,7#~11#及14#~16#为双柱式薄壁空心墩结构,截面尺寸为7m*3.5m。

2 主要施工技术难点

大桥位于贵州高原腹地,跨摆捞河,河宽约40m,水流湍急,桥轴线通过段地面高程为647-750.5m之间,相对高差103.5m,凯里岸基岩大部裸露,羊甲岸局部基岩出露,地表受溶蚀、冲蚀作用强烈,地形条件复杂,高低起伏,且空心薄壁墩全部坐落在谷底,受高度和地形限制,材料的水平和垂直运输比较困难;该桥墩柱形式多样,截面尺寸不一,墩高壁薄,平均墩高72m,对墩身混凝土的整体性和墩中心线的控制要求极为严格,工艺水平要求较高;贵州潮湿多雨,施工期间不可避免遇到降雨,必須采取有效措施降低降雨对墩柱施工的影响;本工程附近无河砂可用,只能采用机制砂,施工中应考虑机制砂对墩柱的质量影响。

3 施工方案比选及优缺点分析……