地铁车站柱下端承桩施工技术研究

2018-05-02杨兵

杨兵

【摘 要】深圳地区主要使用的两种端承桩型,一是钻(冲)孔灌注桩,二是预应力管桩。针对两种端承桩型分别以不同岩层做持力层的情况,论文结合深圳地铁10号线1011-3A标工程,阐述柱下端承桩施工工艺,并通过整理工程实测数据以及工程出现的问题,总结了地铁柱下桩桩端持力层的主要缺陷与危害,并归纳了持力层承载力不足的处理的工程技术对策。

【Abstract】There are two kinds of end-bearing piles mainly used in Shenzhen area, one is drilling (punching) hole cast-in-place pile, and the other one is prestressed pipe pile. Aiming at the case of two kinds of end-bearing piles with different strata as bearing layers, combines the 1011-3A section of Shenzhen Metro Line 10 project, this paper expounds the construction technology of end-bearing piles at the bottom of column, through sorting out the measured data and engineering problems, it summarizes the main defects and hazards of the bearing stratum of end-bearing piles at the bottom of column of the subway, and sums up the engineering technical countermeasures for the treatment of the insufficient bearing capacity of the holding layer.

【關键词】柱下端承桩;持力层;底板预留

【Keywords】 end-bearing piles at the bottom of column; bearing layer; bottom floor reservation

【中图分类号】U231.3 【文献标志码】A 【文章编号】1673-1069(2018)04-0183-06

1 工程概况

孖岭站是深圳轨道交通10号线工程的第7个站,为地下四层岛式换乘车站,车站主体结构采用现浇整体式框架结构,车站左线起点里程ZDK7+239.340,右线起点里程DK7+248.340,车站有效站台中心里程为DK7+367.500,终点里程为DK7+477.540,车站左线长238.20m,右线长229.20m。车站全长238.20m,基坑深度约25.1-26.1m(南端头基坑深度26.1m),深度嵌入底板下4.5-9.5m,南端头位置连续墙位于底板下右线8.4、左线8.5m。(图1)

车站南端头地质从上到下依次为素填土4.52m、淤泥质黏土0.56m、粗砂1.48m、粉质黏土3.07m、粗砂2.42m、砂质粘性土2.47m、全风化混合岩5.67m、土状强风化混合岩9.51m、中风化混合岩2.62m、微风化混合岩。(图2)

车站采用1000mm厚地连墙+内支撑系统;车站标准段采用五道支撑,其中第一、第四道为钢筋混凝土支撑,第二、三、五道为钢管支撑;车站南端头采用五道钢筋混凝土支撑。

其中支撑及混凝土腰梁截面为800*1000mm,底板厚1300mm。

2 柱下端承桩施工情况

在主体结构双数轴线位置设置柱下端承桩桩,桩径1.5m,柱下端承桩采用钻孔灌注桩施工,应确保每根桩桩端进入中风化层中H不小于4m,或进入微风化层不小于1.5m。……