基于熵权灰色关联模型的PPP项目风险评价
2018-02-08刘兴旺
刘兴旺
摘要: PPP作为一种新的融资模式,其存在的风险问题一直备受关注。针对项目各参与方承担的风险难以准确定义及量化、风险难以合理分担等问题,通过建立PPP项目的16个主要风险评价指标,运用熵权法对其风险因素权重进行定量确定。最后运用灰色关联模型,确定了各参与方承担的主要风险。
Abstract: As a new financing model, PPP has long been a topic of risk. According to the difficulty of accurately defining and quantifying the risk assumed by each participant in the project and reasonably sharing risk, through the establishment of 16 major risk evaluation indexes of PPP projects, the weights of risk factors are quantitatively determined by using the entropy method. Finally, using the gray relational model, the main risks borne by each participant are determined.
关键词: 公私合营(PPP)模式;熵权法;灰色关联;风险评价
Key words: public-private partnership (PPP);entropy weight method;grey correlation;risk evaluation
中图分类号:F283 文献标识码:A 文章编号:1006-4311(2018)07-0083-04
0 引言
PPP模式(public-private partnership,公私合伙/合营)是指政府为提供公共产品和服务与私营企业建立的长期合作伙伴关系,包含BOT、PFI等多种方式。与BOT相比,PPP更强调的是政府在项目中的参与,更强调政府与企业的长期合作与发挥各自优势,共享收益、共担风险和社会责任[1]。然而PPP融资模式也存在着不足与缺陷,风险在PPP项目过程中对项目目标和绩效的实现至关重要,因此公共部门和私营部门很有必要在PPP项目合同谈判阶段客观评估整个项目生命周期中存在的潜在风险。

风险识别、风险评估和风险处置一直被认为是项目风险管理的三大核心组成部分。风险识别的技术一般包括信息搜集技术(包括头脑风暴法、德尔菲法、访谈、SWOT分析)、核对表分析、假设分析和图解技术(包括因果图、系统流程图、影响图)[1]。大多数方法都曾应用于PPP项目的风险研究中,例如,Li将PPP项目风险分为宏观、中观和微观3个等级[2];风险评价方法可以分为风险定性分析方法和风险定量分析方法[3],Akintoye和MacLeod等人都做过相应的问卷调查,结果表明基于专家的经验判断和主观评价的风险定性分析方法是工程领域中常用的风险评估方法[4]。……