500kV输电线路大跨越基础超长灌注桩群桩施工
2017-10-21王明新
王明新
摘要:对于超长的灌注桩而言,其通常是在对输电线路的基础进行施工时,需要用到的一种对基础进行处理的方法。由于输电线路的距离相对较长,因此在对其基础进行施工时,施工的质量会受到地质条件的影响,采用灌注桩的方法进行施工,可以有效地保证基础的承载力达到要求,本文着重分析了大跨越基础超长灌注桩的群桩施工,以此来供相关人士交流参考。
Abstract: Super long bored pile is a commonly used method of foundation treatment in transmission line foundation construction. Because the transmission distance is relatively long, the construction quality of the foundation will be affected by geological conditions. Using the bored pile construction method can effectively ensure the foundation bearing capacity to meet the requirements. This paper focuses on the analysis of the pile group construction of large span foundation super long bored pile, in order to provide reference for relevant personnel.
关键词:输电线路;大跨越基础;超长灌注桩;群桩施工
Key words: power transmission line;large span foundation;super long bored pile;pile group construction
中图分类号:TU753 文献标识码:A 文章编号:1006-4311(2017)32-0090-02
0 引言
目前的施工过程中,由于受到地质条件的影响,施工人员在对基础进行处理时,也研究出了多种施工方法来有效地提升了地基的承载力,其中常用的技术方法就是灌注桩施工技术,对于大跨越基础进行处理时,采用灌注桩基础可以有效地提升基础承载力。由于其施工的距离过长,因此在施工过程中施工人员一定要对每一道施工工序进行控制,保证施工完成之后,其质量可以满足设计的要求。
1 施工的原理
在利用灌注桩技术进行施工时,其具体的施工原理为正循环回转钻进成孔;也是施工人员在利用此技术对大跨越基础进行处理时常用的施工原理。此项技术符合国家电力建筑桩基技术规范,且能够为国家节约施工成本,降低耗损,从而为国家电力设施建设做出更大贡献。
2 施工的工艺
2.1 造浆
在进行造浆时,施工人员首先要熟悉施工现场的环境,并根……