洞湾隧道进口段岩溶发育特征分析与施工处理建议

2016-09-30何以文

建筑科技与经济 2016年2期
关键词:处理措施

何以文

摘 要:隧道岩溶问题是当前国内外隧道施工中的重大难题,岩溶工程地质问题对地下工程建设和运营管理造成很大的影响。洞湾隧道施工过程中发现隧道底板以下发育大型溶洞,通过配合测量断面同时进行地质水文地质调绘、物探结合钻孔详细查明溶洞规模、形态、大小、埋深及与线路的关系,查明隧道底板以下岩溶发育情况以及与隧道顶板的距离,评价隧道围岩的稳定性,并提出岩溶施工处理措施建议,为隧道施工及岩溶整治设计提供地质依据。

关键词:洞湾隧道; 岩溶工程地质问题; 围岩稳定性; 处理措施

Abstract: Karst problem is a major problem in the current domestic and international tunnel construction, a lot of impact on karst engineering geological problems of underground construction and operations management. Tunnel construction process, the following development of a large cave in the tunnel backplane holes Bay geological hydrogeological tone painted simultaneously with the measurement section, borehole geophysical combination of detail to identify the scale of the cave, the shape, size, depth, and the relationship with the line, to identify the distance of the metro plate karst tunnel roof, the evaluation of tunnel surrounding rock stability, and put forward the proposal of the karst construction measures, to provide the geological basis for the tunnel construction and karst remediation design.

Key words: hole Bay Crossing; karst engineering geological problems; surrounding rock stability; treatment measures

1.引言

在建洞湾隧道属贵州省赤水至望谟高速公路重难点和控制性工程,隧道采用分离式,其中:左洞起讫桩号ZK66+164~ZK68+290,总长2126m;右洞起讫桩号YK66+205~YK68+290,总长2085m。隧道净空10.25×5.0m,隧道最大埋深约310m。当隧道开挖到右线右壁YK66+488里程处揭露出大型溶洞,根据施工情况和现场初步调查,从隧道底往上发育约13m,隧道顶板和右侧壁坍塌;往下垂深发育30~40m,在隧道以下形成多个溶洞大空腔,相互连通。溶洞顶离设计隧道底最薄处约3~5m。导致中断施工近五个月,直接影响隧道的施工和安全。但溶洞具体如何展布?发育特征如何?与隧道的关系不清。其危险程度取决于溶洞的规模、溶洞周围岩体的稳定性和岩体的质量及其与隧道的关系[1]。

2.隧道区地质背景

隧道区属构造溶蚀侵蚀中低山地貌,处于川黔南北向构造带与北东向构造带交接的复合部位,北与新华夏系第三沉降带的“四川盆地”相接,南与早古生带“黔中隆起”相邻,构造形迹定形于印支~燕山期,多呈北东向展布。……

登录APP查看全文

猜你喜欢

处理措施
微创治疗高血压脑出血术后相关并发症的原因及处理
经皮肾镜取石残留结石的原因分析
电力系统继电保护故障分析与处理措施探讨
简析道路桥梁施工中对于软弱地基的处理措施
某电厂2号机OPC信号复位后EH母管油压低跳机原因分析
电厂机组负荷摆动分析以及处理研究
一千瓦电视发射机常见故障及处理措施
浅析三门核电厂设备冷却水系统运行失效和处理措施
青海油田尕斯第三采油作业区管道结垢影响因素及治理方法
高低压配电设备常见故障与处理之我见