铁路工程简支T梁不同运架方式施工工艺及经济性比选
2025-08-24文琪
中图分类号:U445 文献标志码:A 文章编号:1003-5168(2025)13-0085-04
DOI:10.19968/j.cnki.hnkj.1003-5168.2025.13.017
Comparison of Construction Techniques and Economic Efficiency Among Different Transport and Erection Methods for Simply Supported T-beams in Railway Engineering
WEN Qi
(Zhengzhou Design Institute, China Railway Engineering Consulting Group Co.,Ltd., Zhengzhou 450001, China)
Abstract: [Purposes] This paper aims to evaluate the selection of different transport and erection methods for simply supported concrete T-beams in railway engineering,with the objectives of maximizing resource utilization effciency,optimizing construction process sequencing,and ultimately improve the overall performance of railway construction projects.[Methods] The differences between railway and highway methods for transporting and erecting simply-supported T-beams are thoroughly analyzed using methods such as literature review,field investigation and dataanalysis.[Findings] Through computationalanalysis,itis found that475km is thecritical thresholdof transport distance.When thetransport distance exceeds 475km,railway transportation is more cost-effective,while highway transportation is more economical for distances less than 475 km.[Conclusions] The selection of the railway simply supported T-beam transportation and erection methods needs to be decided comprehensively according to the transport distance,transportation and erection methods,and equipment conditions.The establishment of the critical transport distance model analysis shows that this method significantly reduces the comprehensive cost and shortens the construction duration,and provides a reusable economic compari
son framework for similar railway engineering
Keywords: simply supported concrete T-beam; railway beam transportation; highway transportation of beams; erection of bridge erecting machine field investigation; data analysis
0 引言
铁路交通的快速发展,对铁路桥梁建设的质量、效率和经济性提出了更高的要求。简支T梁作为一种常见的桥梁结构形式,因其结构简单、受力明确、施工便捷等特点,在铁路桥梁建设中得到了广泛运用[1]。然而,不同的运架方式对施工质量和成本有着显著影响。因此,采用恰当的运架方式对于保障工程质量,提高施工效率,以及减少建设成本至关重要。本研究通过构建临界运距模型,并对不同运架方式的优缺点进行分析,解决了铁路简支T梁在不同里程及设备条件下运架方式的选择难题,研究成果对类似项目的成本控制、工期管理及技术方案的选择具有一定的参考价值。
1概况
1.1 项目概况
东明华汪热力铁路专用线位于山东省菏泽市东明县,该专用线自东明县站东咽喉北侧接轨引出,并行新充线向东下穿既有东兰公路桥,跨过万福河后,左转绕赵官营村东南折向北,依次跨越五四路、三八路、日东高速公路等。专用线正线长10.057km ,桥梁长 4.49km ,其中简支T梁桥长4.39km ,共计101孔。
1.2 研究方法
首先,对各种运架方式进行调查分析,了解其施工工艺和技术特点;其次,对实际工程现场进行调查,了解各种运架方式的应用情况及优缺点;最后,通过数据分析对各种运架方式的经济性进行比选。本研究将从运输及架设两方面进行对比分析,以便深人剖析火车运架和汽车运架简支T梁的
投资差异。
1.3 现状调查
1.3.1工程现状调查。……