新型悬挑脚手架施工技术的应用

2021-10-31周肖孙昊张雷苏蒋新建丁军

河南科技 2021年15期

周肖 孙昊 张雷苏 蒋新建 丁军

摘 要:本文以扬子江药业集团上海学术科研中心项目为载体,创造和总结出一套适用于装配式结构的新型悬挑脚手架施工工艺,弥补了传统悬挑脚手架的不足,为后续大量PC项目采用新型悬挑脚手架施工提供技术支持和具体经验。

关键词:新型悬挑脚手架;花篮拉杆;高强螺栓;施工工艺

中图分类号:TU731.2文献标识码:A文章编号:1003-5168(2021)15-0088-04

Abstract: Taking the Shanghai Academic Research Center project of Yangtze River Pharmaceutical Group as the carrier, this paper creates and summarizes a set of new cantilevered scaffolding construction techniques suitable for prefabricated structures, which makes up for the shortcomings of traditional cantilevered scaffolding, and provides technical support and specific experience for the construction of new cantilevered scaffolding in a large number of subsequent PC projects.

Keywords: new cantilever scaffolding;flower basket tie rods;high-strength bolts;construction technology

扬子江药业集团上海学术科研中心项目为地下2层、地上19层(局部4层裙楼)的框架结构,总建筑面积为83 915.87 m2,其中,地上面积为58 846.83 m2,地下面积为25 069.04 m2。该项目采用装配整体式混凝土框架和现浇混凝土核心筒,相比传统悬挑脚手架,新型悬挑脚手架制作简单,使用方便,周转率高[1-3]。

1 施工中遇到的问题

本工程为装配整体式混凝土框架-现浇混凝土核心筒结构,主体结构梁为预应力混凝土(PC)梁,传统悬挑脚手架的工字钢需要穿过外墙板,固定在叠合楼板上,而U形锚环埋入叠合楼板施工不便,无法针对现场进行调整,且后期修补困难[4]。

2 解决方案

针对施工中存在的问题,进行悬挑脚手架优化设计,采用新型悬挑脚手架施工,避免在楼板上留置工字钢洞、叠合板内预埋U形锚环。下面分析具体优化方案。

3 组合式悬挑脚手架结构布置

3.1 挑梁要求

本项目悬挑主梁采用16#工字钢作为悬挑式盘扣脚手架,钢管规格为A48 mm×3.0 mm,主要立杆纵距为1.5 m;立杆横距为0.9 m;水平杆步距为2 m;架体外侧纵向每5跨每步设置一根竖向斜杆,悬挑层开始搭设时,利用拉杆固定工字钢,顶部用高强螺栓连接,底部用钢拉杆与吊耳板连接。……

登录APP查看全文