APP下载

槽形梁横移施工方案分析

2021-10-31肖文贵

河南科技 2021年15期

肖文贵

摘 要:本文通过简单分析兰州市彭家坪210#路K1+010.75节点的32 m槽形梁桥工程,提出相对应的施工方案。其间从桩基施工、钢管及贝雷梁施工、滑道施工、槽梁横移、落梁施工5个方面进行详细的分析,以期为槽形梁横移施工提供一些参考。

关键词:桥梁工程;槽形梁;横移施工

中图分类号:U445.4文献标识码:A文章编号:1003-5168(2021)15-0082-03

Abstract: Through a simple analysis of the 32 m channel girder bridge project at K1+010.75 node of Pengjiaping 210# Road, Lanzhou City, the corresponding construction plan is proposed in this paper. In the meantime, a detailed analysis is carried out from five aspects, namely pile foundation construction, steel pipe and Bailey beam construction, slide construction, trough beam lateral movement and drop beam construction, in order to provide some references for trough beam lateral movement construction.

Keywords: bridge engineering;trough beam;lateral construction

兰州市彭家坪210#路K1+010.75节点的32 m槽形梁桥为柳陈联络线改造工程,本桥既有跨度为8 m,新建跨度为32 m,采用线路一侧预制槽梁,预制完毕后将槽梁移至设计位置。施工主要内容包括桩基施工、支架搭设、贝雷梁吊装和滑道铺设,待滑道铺设完成后进行梁体横移,槽梁到达设计位置后,进行滑道及支架拆除、支座安装等施工。

1 施工过程

1.1 桩基施工

在进行桩基施工时,桩顶应预埋固定钢板,并根据支架、贝雷梁、滑道以及梁体就位后的设计标高,准确测量桩顶标高,即预埋钢板顶标高。

1.2 钢管及贝雷梁施工

钢管支墩運用钢管制作立柱,钢管的型号是[Φ]603 mm×12 mm,布设方式是竖桥向设计4排钢管,横桥向配备4根钢管,不同钢管间设立水平方向的连接系,端头两侧钢管间设立竖向连接系构成完整的支墩。

1.2.1 钢管立柱搭建。布设到桩基础的钢管立柱在作业过程中预先埋设钢板,钢管立柱和钢板间使用焊接方式连接。钢管接长运用对接接长方式,相应的钢管接头使用双面焊接方式,外在形状查看达到要求后在外侧将缀板焊上。其中,缀板的尺寸是300 mm×292 mm×10 mm,各个接头都配置4块缀板,其间将型号为[Φ]550 mm×10 mm的钢管分割成6块,得到缀板。……

登录APP查看全文