城市复杂环境下水塔爆破拆除的应用
2021-08-06蒙海霖程贵海覃翔
蒙海霖 程贵海 覃翔



【摘 要】论文针对一个钢筋混凝土水塔作出拆除爆破方案设计,该水塔采取东南方向定向倒塌的方式。论文对爆破切口和定向窗进行确定,采用数码电子雷管起爆,确保了炮孔起爆的安全性和延时准确性。针对工程复杂环境采取一系列安全防护措施,有效实现该水塔安全快速拆除,为同类拆除工程提供借鉴。
【Abstract】In this paper, the demolition and blasting design of a reinforced concrete water tower is made. The water tower adopts the way of directional collapse in southeast direction. In this paper, the blasting incision and directional window are determined, and the digital electronic detonator is used to ensure the safety and delay accuracy of blasting hole. In view of the complex environment of the project, a series of safety protection measures are taken to effectively realize the safe and rapid demolition of the water tower, which provides reference for similar demolition projects.
【关键词】复杂环境;水塔拆除爆破;数码雷管
【Keywords】complex environment; water tower demolition and blasting; digital detonator
【中图分类号】TU746.5 【文献标志码】A 【文章編号】1673-1069(2021)05-0190-03
1 工程概况及施工难点
1.1 工程概况
待拆除的旧水塔是位于钦州市北部湾大道钦州铁路地区小区内的钢筋混凝土扇形结构水塔,因钦州铁路地区建设需要对场地内的旧水塔进行拆除,拟采用爆破方法进行拆除。待拆除水塔总高44m,水塔底部有高1m、直径3.8m的基础,水塔下部为圆筒形,筒身高33m,直径3.2m,壁厚0.18m,底部北偏东25°有1个高2.1m、宽0.7m的门,筒体和上部水仓间连接位置高1m,直径3.8m。水塔上部为倒锥形水仓,水仓高7m,直径15m。水仓顶部附属物高2m。水塔内西北侧和西侧有2根直径0.25m的水管,需提前拆除,如图1所示。
1.2 施工环境及难点
①周边环境较为复杂,水塔周围需保护对象较多。最近的居民房距离爆心约有46m,西南角约88m处有小区内部的电力变压器,西侧15m处有村民祠堂,往西北40m处是车流量较大的北部湾大道。②端部水箱为钢筋混凝土结构,具有较强的刚度。在原地卸除筒体垂直方向支撑后,水箱与地面的冲击作用可能不会使水箱发生解体,而产生扩散前冲或滚动的可能。……