移动式电流回路试验平台的研制
2021-07-20金慧波刘洁波单鑫陈文通范旭明
金慧波 刘洁波 单鑫 陈文通 范旭明



[摘 要]电流回路试验是变电站技改大修工程中的重点试验项目,如何提高工作效率至关重要。通过前期科学调研,分析了导致电流回路试验工作效率低的主要原因,针对性研制出移动式电流回路试验平台。经实践证明,移动式电流回路试验平台全方位提升了试验的便捷性和安全性,将变电站单间隔电流回路试验的总时间降低了40%,极大提高了工作效率。
[关键词]电流回路试验;移动式小车;设备一体化;工作效率
[中图分类号]TM633.2 [文献标志码]A [文章编号]2095–6487(2021)03–00–02
[Abstract]The current loop test is a key test item in the technical transformation and overhaul project of the substation. How to improve the work efficiency is very important. Through the preliminary scientific investigation, the main factors that lead to the low efficiency of the current loop test were analyzed, and the mobile current loop test platform was developed targeted. Practice has proved that the mobile current loop test platform improves the convenience and safety of the test in all aspects, reduces the total time of the single-interval current loop test of the substation by 40%, and greatly improves the work efficiency.
[Keywords]current loop test; mobile trolley; equipment integration; work efficiency
随着中国经济的快速发展,全社会用电需求量不断增长,为缓解供电企业的供电压力,除新建变电站外,还需对原有变电站进行技改大修,以保障电能供给的可靠性及电能质量。在变电站的技改大修项目中,二次专业改造具有工作面多、工程量大、耗时长的特点。其中新设备和改造设备投运前的电流回路试验项目多,耗时长,一定程度上拖累了技改进程,增加了用户的停电时间。因此,如何提高电流回路试验的工作效率,减少设备停电时间,保障设备安全投运对于提高电力企业的经济效益,推进“服务型”供电企业的建设具有重大的意义。
1 电流回路试验
在变电站的技改大修项目中,电流回路试验包括一次通流试验[1-2]、CT点极性试验[3]和二次负载试验。在新设备和改造设备投运前,通过电流回路试验验证相应间隔电流回路二次接线的正确性关乎整个变电站的安全稳定运行。……