Abstract: In the process of social and economic development, the process of urbanization is accelerating, and the number of urban populations is increasing. In order to meet people's living and working needs, the number of high-rise buildings is increasing. In the process of high-rise building construction, the foundation construction is particularly important. The use of post-pouring zone construction technology to transform the traditional construction mode can improve the strength of the foundation and the stability of the foundation on the one hand, and on the other hand, ensure the safety and stability of subsequent projects. This article discusses the construction technology of post-pouring zone in the foundation of high-rise buildings, and provides a reference for the application of post-pouring zone technology.
关键词:高层建筑;基础;后浇带施工;探讨
Key words: high-rise building;foundation;post-pouring zone construction;discussion
中图分类号:TU755 文獻标识码:A 文章编号:1006-4311(2020)23-0133-02
0 引言
高中建筑基础施工过程中,基础项目是重要组成部分。在基础施工期间,会在基础结构中设置变形缝,变形缝的主要作用,在于有效处理混凝土收缩变形产生作用,主要为挤压作用,利用变形缝抵抗产生的收缩压力。在变形缝施工期间,应用后浇带施工技术,既能保证混凝土结构保持良好的连续状态,还能提高变形缝抵抗结构压缩的能力,从而提高基础的施工质量。
1 后浇带概述
1.1 后浇带的概念
在进行混凝土浇筑施工时,混凝土随着时间的推移,内部会出现水化热反应,水化热反应会释放出较多的热量,致使混凝土内部温度较高,与外部温度产生明显的温度差,在温度差作用下,混凝土出现收缩等情况。在混凝土结构的接触位置,需要设置变形缝,利用变形缝抵御混凝土变形产生的影响。一般将变形缝设置在基础底板或者墙体连接位置,变形缝可以将混凝土分为多个结构,向结构中进行混凝土浇筑,使不同的结构通过混凝土相互连接,最终形成统一的结构。……