百万机组汽轮机安装过程中的质量保障措施探析
2018-09-20朱加庆
朱加庆
摘要:现阶段,电力对于社会经济发展的重要性不言而喻,任何一个行业对于电力资源的依赖性也是大大的提升。在这样的背景下,就要求发电厂必须确保其能够安全稳定的提供电力供应。在发电厂中,汽轮机发挥着十分重要的作用,其安装工作在火力发电厂建设中是一项十分重要的工作。汽轮机安装工艺直接关系到发电机组的安全稳定运行和经济效益。
Abstract: At this stage, the importance of electricity to social and economic development is self-evident, and the dependence of any industry on power resources is greatly enhanced. In this context, power plants are required to ensure that they are able to supply electricity safely and steadily. In power plants, steam turbines play a very important role, and their installation work is a very important task in the construction of thermal power plants. The turbine installation process is directly related to the safe and stable operation and economic benefits of the generator set.
关键词:汽轮机;安装工艺;质量保障;措施
Key words: steam turbine;installation process;quality assurance;measure
中图分类号:TM621 文献标识码:A 文章编号:1006-4311(2018)28-0042-02
0 引言
当前,随着社会经济的快速发展,火电行业逐步向大型高效机组的方向发展。目前,大型超超临界汽轮发电机组技术日趋成熟,电力市场上出现了明显的供不应求现像,同时火电工程建设周期非常紧凑,导致安装常规的安装施工工序,很难满足工程施工进度要求。本文结合工程实际,通过对百万超超临界汽轮机安装工艺工序技术要点进行总结,以期制定可行的安装方案,从而提高超超临界汽轮机的安装水平,确保机组能够长期安全、稳定、高效地运行。
1 百万机组汽轮机概况及主要安装工序、要点
1.1 百万机组汽轮机概况
国电泰州电厂二期工程所选用的1000MW汽轮机组为上海汽轮机有限公司制造的单轴五缸四排汽汽轮机,超高压缸、高压缸、中压缸为整体模块供货,安装时以低压缸为基准进行找正。低压外缸散件供货,现场拼装焊接;低压内缸分上、下两半供货。汽轮机从车头至低压B缸,依次分布有#1~#6轴承座,高压、中压缸的就位方式均为猫爪支撑在前后轴承座上。……