零功率物理试验期间主控室操纵员的配合
2018-04-16赵溪张旭张晓斌
赵溪 张旭 张晓斌
【摘 要】零功率物理试验是换料大修结束后按技术规格书要求需进行的试验,共8项,且每项试验在其过程中均有保持反应堆相关参数稳定的要求,如操作不当,轻则有可能导致试验失败,重则可能导致反应堆停堆。本文作者通过对每项试验进行分析,归类试验中需主控室操纵员配合的操作,并对此类操作进行描述,以降低试验失败或停堆的可能。
【关键词】零功率;物理试验;主控室操纵员;操作
中图分类号: TM623 文献标识码: A 文章编号: 2095-2457(2018)03-0218-002
Coordination of master control room operators during zero-power physics testing
ZHAO Xi ZHANG Xu ZHANG Xiao-bin
(Nuclear Nuclear Power Operations Management Co., Ltd., Haiyan, Zhejiang 314300, China)
【Abstract】The zero-power physics test is a test to be carried out according to the technical specifications after the refueling overhaul, a total of eight, and each test in the process have the requirements to maintain the stability of the relevant parameters of the reactor, such as improper operation, light It may lead to failure of the test, which may lead to reactor shutdown. The author of this article analyzes each test, categorizes the operations that the master control room operator needs to cooperate in, and describes such operations to reduce the possibility of failure or shutdown.
【Key words】Zero power; Physical test; Control room operator; Operation
1 零功率物理试验简介
零功率物理试验,是核电厂换料大修结束后按技术规格书要求所进行的试验,其试验目的是为了验证反应堆核设计的准确性、控制棒价值、硼的价值、慢化剂温度系数计算的准确性等,共有8项,按照其试验前反应堆工况又可归为3大类:热停堆工况、热态零功率工况、核发热点以上工况。
2 以热停堆工况为初始条件的零功率物理试验
《换料后的首次临界试验》,试验要求维持主系统压力15.2±0.2MPa,一回路平均温度280±1.5℃。
由于试验前处于热停堆工况,次临界状态,需依靠控制棒的提升以使反应堆达到临界,此时可将一只大气释放阀置自动,另一只置手动,机操手动控制大气释放阀的开度来维持一回路平均温度,与此同时,还应密切关注两个蒸汽发生器的液位,根据蒸汽量来调整启停给水进入蒸发器的给水流量,尽量保证蒸发器液位平稳,避免出现大幅波动现象。
3 以热态零功率工况为初始条件的零功率物理试验……p>