牛栏口水电站调压井开挖施工
2018-02-01谢朝宗
谢朝宗



【摘 要】牛栏口水电站引水系统调压井为小型调压井,开挖断面为长双园心椭园形,园心半径为8.5m和10m,井高49.5m,土石方明挖4500m3,石方井挖10500m3。由于工程规模小,加之受施工条件的限制,调压井井挖不宜采用机械化施工,溜渣井开挖及扩挖翻渣均采用人工进行。
【关键词】牛栏口水电站;调压井;开挖
Excavation of surge shaft in Niulankou hydropower station
Xie Chao-zong
(China Water Conservancy and Hydropower Ninth Engineering Bureau Co., Ltd Guiyang Guizhou 550000)
【Abstract】The surge shaft of the Niulankou hydropower station is a small surge shaft. The section of the excavation is a long twin park with an elliptical shape. The radius of the center of the park is 8.5m and 10m. The height of the well is 49.5m and that of the earthwork digging is 4500m3. 10500m3. Due to the small scale of the project and the restriction of the construction conditions, it is not appropriate to use mechanized construction to excavate the pressure surge wells, and the excavation and dredging of the slip slag wells are manually carried out.
【Key words】Niulankou hydropower station;Surge tank;Excavation
1. 工程概況
(1)牛栏口水电站位于重庆市石柱县境内的龙河中下游,是龙河梯级开发的第五级,电站装机为2×10MW。引水系统由进水塔、引水隧洞、调压井、压力管道组成。
(2)调压井位于厂房后坡的山体内,为阻抗式调压井。调压井的形状为长双园心椭园形,园心半径为8.5m和10m,井高49.5m。土石方明挖4500m3,石方井挖10500m3,边坡及井壁均设锚杆和喷混凝土支护(调压井开布置图见图1)。
(3)调压井位于引水洞末端2+198.87桩号处,引水洞施工支洞位于引水洞2+147桩号,距调压井中心51.87m,施工支洞长172m。调压井上部平台高程为542.1m,由一条永久道路与厂房相连。
(4)调压井围岩主要为粉砂质泥岩,其间夹有长石砂岩与长石石英砂岩薄层,泥岩的岩性比较完整,但强度较低,易风化崩解,长期暴露易失稳,属Ⅲ类围岩。
2. 施工程序
(1)调压井开挖首先进行厂房至调压井永久公路施工,形成进场公路,为调压井上部开明挖创造条件,同时进行下部施工支洞的开挖,为调压井扩挖提供出渣通道;
(2)调压井上部明挖结束后,立即进行溜渣井的开挖,溜渣井采用人工从上至下开挖,开挖直径为2.5m;由于调压井断面较小,扩挖时翻渣只能采用人工翻渣,开挖形成漏斗型分层开挖,因此扩挖翻渣及施工安全是本工程的一大难点。……