总价措施项目费不合理报价影响合同执行

2017-11-04李明王良栋付国河

中华建设科技 2017年9期
关键词:施工

李明 王良栋 付国河

【摘 要】倒虹吸工程投标文件中总价措施项目清单施工期排水费16.5525万元,由于没有充分研究水文地质资料,对施工降水困难估计不充分,实际发生的施工降水费用7679.4185万元,造成工程后期资金紧张,严重影响合同执行。

【关键词】总价措施项;施工期降水费

The total price of the project is unreasonable to affect the implementation of the contract

Li Ming1,Wang Liang-dong2,Fu Guo-he3

(1.ID number:410883198805260019;

2.ID number:410322198507093814;

3.ID number:410421199003070030)

【Abstract】Inverted siphon project bidding documents in the total price of the project list of construction period drainage fee of 16.5525 million yuan, due to the lack of adequate study of hydrogeological data, the construction of difficult to estimate the precipitation is not sufficient, the actual construction of precipitation costs 7679.4185 million, resulting in late funding , Seriously affecting the implementation of the contract.

【Key words】The total amount of measures;Construction period of precipitation

1. 引言

本工程由进口连接渠道段、进口闸室段、倒虹吸管身段、出口闸室段和出口连接渠道段组成,工程总长共计1550m。其中两端渠道总长374m,进口渠道段长99.4m,出口渠道段长274.6m;倒虹管身段水平投影长1015m,进口渐变段、闸室段长68m,出口闸室、渐变段长93m。施工区内地下水位高程为88.6m,倒虹吸建筑物位于地下水水位以下,需进行降水施工。从2009年4月开始进行降水,先后组织了2次降水试验、3次大的降水方案的调整后,历经7个月的时间,才基本满足换填施工要求,随着基坑降水漏斗基本形成并逐步稳定及换填的结束,降水施工转入常态。由于施工期降水量较勘探期降水量大、地下分水岭发生变化、地下水补给量和补给范围较招标文件描述的大、2010年8月18日暴雨洪水灾害导致地下水位上升、渗透系数K实际值较招标文件提供的K值发生变化,导致实际施工降水方案较招标文件确定的降水方案发生了变化,大大增加了该工程的施工难度及施工成本。

2. 降水工程

基坑降水经历了试验性降水、强降水、常态降水三个阶段,降水过程简述如下:

2.1 试验性降水阶段。

2.1.1 前期试验性降水于2009年4月开始进行,总长143.4m,地下水位88.6m,基坑开挖底部高程82.7m,要求基坑水位降至82.0m。……

登录APP查看全文

猜你喜欢

施工
后浇带施工技术在房建施工中的运用
铝模板在高层建筑施工中的应用
后浇带施工技术在房建施工中的践行探索
新型环保建筑材料在土木工程施工中的应用
防渗漏技术在民用建筑施工中的应用
后浇带施工技术在房建施工中的应用
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
防渗漏施工技术在房建施工中的应用
土木工程施工实习的探讨与实践