深水裸岩双壁钢围堰的设计及施工
2017-11-04邓海洪
邓海洪
【摘 要】双壁钢围堰为大中型跨水域桥梁下部结构常规施工方法,本文以柳州市白沙大桥为例,详细介绍双壁钢围堰在深水裸岩区域的设计与施工。
【关键词】裸岩;深水;双壁钢围堰;爆破
Design and Construction of Double - wall Steel Cofferdam for Deep Water
Deng Hai-hong
(China Railway Engineering Group Southern Engineering Consulting Co., Ltd Zhuhai Guangdong 519000)
【Abstract】Double-wall steel cofferdam for large and medium-sized across the waters of the conventional construction method of bridge foundation based on the liuzhou baisha bridge as an example, introduced in detail the double-wall steel cofferdam bare rock in the deep area of design and construction.
【Key words】Bare rock;Deep water;Double wall steel cofferdam
1. 引言:双壁钢围堰具有制作方便、抗水压、施工迅速、适应面广等优点,给深水桥梁下部施工带来无水施工环境。设计施工人员对工程现场环境条件进行充分了解,并在此基础上制定科学而富有针对性的施工方案,确保钢围堰施工安全顺利地进行。
2. 工程概况
(1)白沙大桥位于柳州市河东大桥和壶东大桥之间,西起柳北区跃进路东至河东片区高新三路与海关路交叉口,全长1920m。白沙大桥主要分为主桥与引桥两大部分,主桥为2×200m单塔双索面斜拉桥。其中主塔采用8根300cm分离式桩基础,承台为矩形承台,横桥向宽12m,纵桥向长27.5m,高8m。承台施工采用钢围堰施工工艺,钢围堰设计为双壁形式,壁厚1m,尺寸为27.6m×12.1m(箱内尺寸),根据柳江水位情况设定围堰顶标高为79.5m,高于常水位2m,封底混凝土顶标高为64.0m,围堰总长度为18.5m,共分为三节,首节长度为6.5m,二、三两节长度为6m。内支撑采用630×8mm钢管,围檩采用I45a双拼工字钢。
(2)桥位处河床面为裸岩地质,卵石覆盖层仅为0.3m~0.7m高,根据封底混凝土标高,围堰需要嵌入岩层3m左右,需要采用爆破施工后清渣方可下放围堰,特定环境给围堰施工增加了极大的难度(双壁钢围堰平面布置图见表1)。
3. 水下爆破
河床设计开挖覆盖层后可进行控制爆破,覆盖层(砂卵石)开挖边坡取1:3,按规范要求,超宽值取3.0m,超深值取0.5m。……