桩板墙在铁路路堑高边坡防护施工中的工艺技术探讨

2017-07-10孟建创

价值工程 2017年20期

孟建创

摘要: 桩板墙是一种新型的支挡结构,其原理是将钢桩插入到稳定地层中或者通过钢筋混凝土挖孔桩作为主要侧向受力构件,桩间再安装挡土板,利用挡土板后填土并通过挡土板将侧向荷载传递至桩身的直立板条状构件形成的挡土结构物。近些年来,钢筋混凝土桩板墙已广泛应用于铁路路堑高边坡防护中。本文介绍了铁路路堑高边坡桩板墙的施工工艺工法以及施工中的一些体会,可作为同类工程的经验借鉴。

Abstract: Pile wall is a new type of retaining structure. The principle is that the steel pile is inserted into the stable strata or through the reinforced concrete digging pile as the main lateral force member, and the retaining plate is installed between the piles. The soil is filled and the lateral load is transferred to the pile structure of the pile. In recent years, reinforced concrete pile wall has been widely used in railway cutting high slope protection. This paper introduces the construction technology and the construction experience of high cutting slope pile wall in railway, and can be used as reference for similar projects.

关键词: 桩板墙;桩体开挖;光面爆破;挡土板

Key words: pile wall;pile body excavation;smooth blasting;retaining slab

中图分类号:U418.5+2 文献标识码:A 文章编号:1006-4311(2017)20-0131-03

0 引言

桩板墙的成功实施,首先应了解并掌握设计地质勘探地层资料,针对不同的地层岩土力学特性,比选出最优的组合式桩体开挖方案。本文就所施工的铁路工程实例为对象,对桩板墙的实际应用进行了工序工艺技术上的探索和探讨。

1 工程概况

新建铁路连云港至镇江铁路DK300+068.75~DK300+171.25路基段设置桩板墙对山体边坡进行滑塌防护。

本工程DK300+068.75~DK300+171.25左侧设C35钢筋混凝土桩板墙支护,第一排桩DK300+068.75~DK300+171.25,1种桩型,计21根,桩截面尺寸为2.5m×2.75m,桩间距(中~中)均为5m,桩长17m~20m;第二排桩DK300+069~DK300+156,1种桩型,计18根,桩截面尺寸为2.0m×2.25m,桩间距(中~中)均为5m,桩长11m~14m。锚固桩身采用C35钢筋砼灌注,侧沟平台以上部分于桩两侧设厚0.4、宽0.3牛腿,牛腿长度随桩悬臂段长变化。锚固桩基坑采用C15钢筋混凝土护壁,厚0.3m。

2 工艺工法

2.1 工艺流程(图1)

2.2 地质条件

根据设计地质勘探资料,桩板墙区域内从上至下地层地质条件具体如表1。……