【摘要】土贤庄水电站,该站变压器,低压侧负荷较大,主要为工业和生活照明用电,完全能够吸收电站所发电量。该电站在系统中担任基荷运行,无调节能力。本文主要阐述其布置方式。

【关键词】土贤庄水电站;布置方式;电气工程设备

Electrical Engineering Arrangement of Tuxianzhuang Hydropower Station

Han Ning

(Shijiazhuang Irrigation District Administration Bureau of Hebei ProvinceShijiazhuangHebei050000)

【Abstract】Soil Yinzhuang hydropower station, the station transformer, low side load is large, mainly for industrial and residential lighting electricity, fully able to absorb the power generation capacity of power stations. The power station in the system as a base load operation, no adjustment capacity. This article mainly elaborates its arrangement way.

【Key words】Tiexianzhuang Hydropower Station; Arrangement; Electrical Engineering Equipment

1. 电站与电力系统的连接

土贤庄水电站位于石家庄市东二环与石津总干渠交叉口的土贤庄跌水处,系石津总干渠梯级电站规划的第三级水电站,装机2×2000KW土贤庄电站西面约1.4Km处有一处红光变电站,其电压等级为110/10KV,隶属华北电网。该变电站现有SFL-20000型和SFZL7-31500型两台变压器,低压侧负荷较大,主要为工业和生活照明用电,完全能够吸收电站所发电量。电站建成投产后以一回10KV线路并入该变电站低压侧母线,输送容量为5630KVA,无穿越功率。该电站在系统中担任基荷运行,无调节能力。

2. 电气主接线布置方式

根据选定的2台2000KW装机方案,本站主接线采用发电机-变压器组扩大单元接线,此接线型式其优点是减少了主变压器和主变高压侧断路器的数量,接线简化,运行可靠,操作维护方便,占地面积小,节约投资,便于布置配电装置。其缺点是当主变故障或检修时,单元内的发电机都将停止运行。

3. 主要电气工程设备

3.1主变压器。

主变选用一台S10-5000/10型变压器,视在功率5000KVA;高压侧额定电压10KV,额定电流288.6A;低压侧额定电压6.3KV,额定电流459A。主变压器布置在户外变压器池内,采用地下电力电缆接入红光变电站。

3.2断路器及隔离开关。

断路器选用ZN63A-12/630型真空断路器,该型断路器额定电压12KV 、额定电流630A、额定频率50Hz,完全满足发电机和变压器并网负荷要求。……