临沂市建设工程规划竣工测绘心得前期准备
2016-05-14董冲
董冲
【摘要】城市建设工程竣工测绘,顾名思义,就是在建设项目完成后,按照竣工测绘标准对项目实地进行测量并与规划审批图纸进行比较的过程,是建设工程规划验收的前期工作。对于竣工测量,前期工作做得越细致,后期工作就做得越快越好越顺畅,返工的可能性就越小,越能提高工作效率。
【关键词】竣工测绘;规划验收;测绘步骤;质量控制
【Abstract】Urban construction projects completed mapping, by definition, after the completion of the construction project, completed in accordance with standard mapping project in the field of measurement and drawing with the planning approval process of comparing, it is construction project planning acceptance of the preliminary work. For the completion of the measurement, the more detailed the preliminary work done, he had a very late work more smoothly sooner the better, the less likely rework, the more you can improve work efficiency.
【Key words】Completion of Surveying and Mapping;Planning acceptance;Mapping step;Quality control
城市建设工程竣工测绘,顾名思义,就是在建设项目完成后,按照竣工测绘标准对项目实地进行测量并与规划审批图纸进行比较的过程,是建设工程规划验收的前期工作。具体是测绘建筑物及周边的1:500数字化地形图,测量规划验收要素、立面高度指标及建筑工程平面位置关系,计算建筑面积并按要求填写竣工测绘报告,核实竣工建筑工程的各项规划审批要素是否按要求进行落实,为建设工程规划验收管理提供客观的、准确的建设工程现状测绘成果,作为依法管理的技术依据。
1. 临沂市建设工程规划竣工测绘现状:
随着经济与社会的不断发展,城市的建筑功能越来越多样化,造型越来越美观,造型多种多样,城市规划的作用越来越重要,同时也增加了验收工作的难度,对竣工验收工作的要求也越来越高,顺应社会发展要求,也为了加强规划验收管理,提高管理的科学化、规范化水平,临沂市规划局于2015年10月8日发布《临沂市规划局建设工程竣工规划核实办法(暂行)》,文中明确了规划验收工作中应进行建成的各项规划审批要素,并委托我院进行规划竣工测量工作。……