三峡重庆库区地灾防治工程施工图预算审查的探讨
2015-10-21童湘雄
中铁二院重庆勘察设计研究院有限责任公司 重庆 400023
摘要:结合三峡重庆库区地灾防治工程施工图预算审查,对造价编审流程、施工图预算审查的依据、内容和方法进行了重点研究和分析,并针对施工图预算中存在的重点问题进行总结、归纳和研究,深层次的挖掘产生问题的原因,并有针对性的提出解决措施,以确保三峡重庆库区地灾防治工程施工图预算投资合理确定,并为招投标提供可靠依据。
关键词:三峡库区;地灾防治;预算审查
Abstract:
Combining with the Construction Budget review of the prevention of geological disasters in Three Gorges Reservoir region of Chongqing,the basis,content and methods of the Construction Budget review are mainly discussed and analyzed.Doing summary,induction and research on the key issues of Construction Budget,deeply focusing on excavating the reasons of the problem and finding out the targeted solutions,are to ensure that the Construction Budget of the disaster prevention project in Three Gorges Reservoir Region of Chongqing is reasonable,and they also provide a reliable basis for bidding.
Keywords:Three Gorges Reservoir Area;Geological disaster prevention;Construction Budget review
引言
三峡库区重庆地质灾害防治工程,主要包括重庆市辖区内的滑坡、崩塌、塌岸等应急抢险Ⅰ类、Ⅱ类项目和非应急项目。三峡地灾防治工程施工图预算不仅是设计阶段控制工程造价的重要环节,也是招投标工作中工程量清单和招标控制价编制的重要依据。因此,为确保施工图预算不留资金缺口,并为招投标提供可靠依据,结合三峡重庆库区地灾防治工程预算审查实务,深度剖析施工图预算中存在的问题和探讨性的提出有效措施是必要的和有现实意义的。
1 三峡地灾防治工程设计阶段造价文件编审流程
1.1设计阶段造价文件的编制流程
方案论证比选阶段编制投资估算:根据防治目标,在已审定的地质勘查报告基础上进行编制。应对多种设计方案的技术、经济、社会和环境效益进行论证,并编制工程估算。
初步设计阶段编制投资概算:对防治方案的任务进行分解,提出具体工程实现步骤和有关参数,编制相应的报告及图件,并编制工程概算。……