新建铁路特大桥桥墩施工关键技术研究

2012-10-15佟运辉

城市建设理论研究 2012年20期

佟运辉

摘要:本文主要基于靖宇到松江河铁路白浆河1号特大桥空心薄壁墩施工级数进行探讨,该工程采用高墩液压自升平台式翻模施工方法。在确保施工质量达到内实外美和高空作业安全的前提下,有效缩短了施工工期和降低了施工成本。对国内高桥墩施工采用新技术、新工艺方面具有一定的推广意义。

关键词:空心薄壁桥墩;液压自升式平台;翻模

Abstract: this paper mainly based on JingYu to SongJiangHe railway white plasma river 1 super major bridge construction series hollow thin wall pilla discussed, this project to adopt the high piers of hydraulic ZiSheng platform utility turn mould construction method. To ensure the construction quality to achieve in within the real beauty and aerial work safety, under the premise of effective shorten the construction period and reduce the construction cost. To domestic high bridge pier construction to adopt new technology, new technology has certain significance for popularization.

Keywords: hollow thin-wall piers; Hydraulic jack-up platform; Turn mould

中图分类号:U443.22 文献标识码:A文章编号:

1.工程概况

靖宇到松江河铁路白浆河1号特大桥中心里程DK19+052,全长555.7m,桥垮结构为7×32 m+(48+40+48m)+4×32 m。7~10墩为矩形变截面空心薄壁墩,横、纵桥向坡比为40:1,最高墩为9号墩高63m。7、10墩为桩基础,8、9墩为明挖扩大基础。空心薄壁墩采用高墩液压自升平台式翻模施工方法。

2.总体施工方案

2.1施工顺序

模板加工2套,先施工7、8号墩,塔吊立在7、8号墩中右侧。9、10号墩中右侧。墩施工完成后将塔吊移位到12墩右侧进行11、12、13墩的施工。

2.2模板及操作平台

(1)基本原理和基本结构自升工作平台式翻动钢模板由工作平台、提升架、吊架、模板系统、液压提升设备、附属设备等部分组成。将工作平台支撑于已达一定强度的墩身混凝土上,以液压千斤顶为动力提升工作平台。达到一定高度后平台上悬挂吊架,施工人员在吊架上进行模板的拆卸、提升、安装、绑扎钢筋等。混凝土的浇筑、捣固、吊架移位和中线控制等作业则在工作平台上进行。内外模板各设3层,循环交替翻升。当第3层混凝土浇筑完成后,提升工作平台,拆卸并提升第1层模板至第3层上方,安装、校正后,浇筑混凝土,周而复始,直至完成整个墩身的施工。……