浅谈市政工程造价控制与管理分析及审核
2012-10-15杨瑜
杨瑜
摘要:市政府提出邯郸三年大变样,市政公司更繁忙,市政工程均属干线型工程,且多处于市区内,影响控制因素很多,如地上及地下障碍物、交叉作业、施工作业点多且分散、工期短、质量要求高等客观因素,同时还涉及到政府部门行政指令等要求,所有这些因素都直接或间接地影响着工程投资,若处理不好,投资控制就很难圆满完成[1]。笔者就市政工程造价的控制、审核进行剖析,并提出相应的对策。
关键词:工程造价,控制与管理,分析审核。
Abstract: The city government put forward three years in handan days differently, municipal companies more busy, municipal engineering belong to the main type of engineering, and many in the urban district, many factors influencing control, such as the ground and underground obstacles, crossover operation, construction ZuoYeDian much and scattered, short construction period, the quality requirements higher objective factors, but also related to the government departments such as administration instruction requirements, all these factors are directly or indirectly affect the project investment, if processes is not good, the investment control, it is hard to satisfactorily completed [1]. The author municipal engineering cost, the control of audit analysis and put forward the corresponding countermeasures.
Keywords:The construction cost, control and management, analyze audit.中圖分类号:TU723.3文献标识码:A 文章编号:
一、市政工程造价的问题和原因
1.全面成本管理的观念尚未形成。目前,对于造价管理的理解往往只停留在预结算上,对工程造价的控制,主要侧重于事后核算,即对竣工决算进行审核,对其他阶段的控制显得薄弱。但事实上前期阶段的管理工作是很重要的。
2.设计管理制度不够完善,限额设计未得到全面推行。据统计分析,设计阶段影响工程造价可能性为40%~70%,施工阶段影响工程造价的可能性为5%~25%。
3.施工阶段设计变更随意性大。工程项目应该经过可行性研究和投资额度的审批程序,其工程造价的控制应该按批准的投资额度。但很多建设单位急于项目的开工,又没有做好必要的准备,对投资额度的要求、建筑标准的把握、设计深度的审查、招标文件和承包合同的合理与完善程度没有严格把关,造成边施工边变更,对施工中的工程想改就改,有的项目一改再改,对更改的必要性和合理性没有监督,对更改造成的损失没有相应的责任制约。……