摘要:预应力混凝土变截面连续箱梁施工,是整个桥施工工程的重要组成部分,要保证高架桥的质量安全,就必须从各方面保证桥预应力混凝土变截面连续箱梁施工的质量。本文将对桥预应力混凝土变截面连续箱梁施工质量控制及技术进行论述。
关键词:预应力 , 箱梁施工, 施工工艺
Abstract: the prestressed concrete continuous box girder cross-section of construction, is the whole bridge is an important part of the construction project, to ensure the quality and safety of the viaduct, we must start from the various aspects of the prestressed concrete bridge that variable cross-section of the construction quality continuous box. This paper will be of bridge prestressed concrete continuous box girder cross-section of construction quality control and technology were discussed.
Keywords: prestressed, box girder construction, construction process
中图分类号:TU74文献标识码:A 文章编号:
一、工程概况
主桥墩顶0#梁段位于桥墩上,灌注0#段后给悬臂施工的挂篮提供一个安装场地。0号节段长7m,混凝土有195.44m3。0#段采用支架施工,支架系统由安装于承台上的三角支架承重,承台及承台上的三角支架之上拼装贝雷桁架作操作平台。
二、预应力混凝土变截面连续箱梁施工施工特点
0#梁段是连续T构的中心,是连续梁悬臂浇注施工的关键块件。梁体的受力经0#块通过支座向墩身传递,0#块受力非常复杂,且一般作为施工机具和材料堆放的临时场地,故其顶板、底板、腹板尺寸都较大。结构重要、复杂,且纵向、横向、竖向预应力管道密集,纵横交错,施工难度大。
0#段为大体积混凝土工程,混凝土方量大,强度高,水泥用量多,为减少施工中混凝土膨胀、收缩不均,及温度应力等不利因素,需尽量缩短每次混凝土浇注时间及采取其他有效措施,保证混凝土浇注质量。
(1)工艺流程
0#段支架安装→模板安装→箱梁底腹板普通钢筋安装→预应力波纹管、连接器,钢铰线等预应力系统安装→内模安装→顶板钢筋安装→顶板预应力波纹管、连接器、钢铰线等预应力系统安装→箱梁模板测量检查→模板、普通钢筋、预应力筋等隐蔽工程验收→浇注箱梁砼→养生拆内模→张拉箱梁预应力筋→压浆→封锚→拆外模。……