高层建筑大跨度悬挑梁板施工

2012-06-04冯冲

城市建设理论研究 2012年13期

冯冲

[摘要]:本文介绍了拉索工字钢平台的搭设,并在该平台上搭设普通扣件式钢管支撑系统对高层建筑大跨度悬挑梁板的施工办法。该办法通过工字钢平台和钢丝绳拉索,巧妙地把施工荷载和结构自重传到下面两个结构层,分散了荷载,降低施工对结构的影响,有效减小了支撑架的倾角,提高了支撑架的稳定性。

[关键词]:悬挑梁板,工字钢平台,支撑架,钢丝绳拉索

[abstract] : this paper introduces the lasso platform range layout, and in the platform built on ordinary steel lubular support system is listed for high-rise building long-span cantilever beam slab construction method. The measures through the range platform and wire rope lasso, the ably construction load and structure to weight the following two structure layer, distracted load, reduce the influence of construction of structure, reduce the support frame of dip Angle, improve the stability of supporting frame.

[key words] : cantilever beam plank, range platform, supporting frame, steel wire and cable

中图分类号:TV52文献标识码:A文章编号:

哈麻住宅小区工程,由于建筑设计需要在高度41.3m以上向外侧悬挑一跨梁板,其挑出跨度为4700mm。由于悬挑梁板投影位置处于已开挖的地下室基础边坡上,造成了其支撑体系着力点设计上的困难,为解决这一难题,我们考虑多套方案,并对各种可行方案进行优化,圆满完成了该悬挑梁板的施工,其施工质量满足了设计要求。

1、施工方案确定

为了完成高空悬挑梁板的施工,我们考虑了三个施工方案。方案一:从地下室搭设扣件式钢管支撑架,直至41.3m;方案二:以下二层边梁为支撑点,斜挑搭设扣件式钢管支撑架;方案三:从下二层楼面架设槽钢,斜挑扣件式钢管支撑架架立在槽钢架上。

经分析,方案一为落地式扣件钢管支撑架,搭设量大,工期长,因其细长可能导致支撑体系不稳定。该体系在施工时,施工荷载产生的压缩沉降变形较大,对质量影响较大。方案二则以下二层的边梁为支撑点向外悬挑梁板边缘架设斜向管,斜向钢管倾斜度达到30°,支撑架稳定性差,架设过程中无法解决失稳问题,抗倾覆性差,架设困难。……