曲线顶管施工在市政给排水工程中的应用
2012-06-04王建伟
摘要:给排水工程施工管理,是保证城市各种基础用水设施正常运行的基础,为居民的生产生活提供用水上的保证具有积极且重要的社会意义。本文以某工程排水系统改造工程为实例,就整个曲线顶管施工过程,曲线顶管轨迹控制与纠偏技术 ,曲线顶管施工沉降分析及沉降控制,以及对道路、构筑物和公用管线的保护措施等做了详细阐述。
关键词:市政给排水;顶管控制;管理
Abstract: water supply and drainage engineering construction management, is to ensure that all sorts of urban water facilities based the normal operation of the foundation for the residents of production and life assurance of provide water with active and important social significance. Taking a project drainage system reconstruction project as an example, the curve pipe jacking construction process, the curve track control pipe jacking technology and rectification, curve pipe jacking construction settlement analysis and settlement control, as well as to the road, structures and public pipeline protection measures in detail in this paper.
Keywords: municipal water supply and drainage; Pipe jacking control; management
中图分类号:S276文献标识码:A 文章编号:
1.工程概况
该排水系统改造遗留工程位于市区繁华地段,污水管道走向主要沿着交通繁忙道路,沿线建筑物密集,地下管线错综复杂。污水管为2400 钢筋混凝土管,“F”型接口,采用顶管施工,管道全长约718.2m。工程分7 段顶进,其中3 段为直线顶管;4 段为曲线顶管,包括:汾阳路曲线顶管149.6m(R=600,α=7.4°),桃江路曲线顶管87.6m(R=300,α=11.6°),宝庆路曲线顶管77.9m(R=300,α=11.6°)和复兴西路曲线顶管197.8m(R=600,α=8.0°)。
2. 曲线顶管施工
整个曲线顶管过程分为四个阶段:出洞前准备阶段、正常顶进阶段、曲线段顶进、出洞及后期收尾阶段。
3. 曲线顶管轨迹控制与纠偏技术
3.1 顶管自动测量引导系统。
测量对曲线顶管的轨迹控制至关重要。由于在曲线顶管管内,测量仪器不能与机头通视,而且在顶进过程中,整体管道都是处在无规则动态,还会发生旋转现象。若采用人工地下导线测量方法,不仅测量时顶管必须停止,而且工作量大,影响顶管进度。在二次测量之间,只能盲目顶进,顶管质量难以得到可靠保证。为此,引进了国内先进的顶管自动测量引导系统,实现了机头的跟踪测量,做到“随测随纠”,有效地保证了顶管的质量并大大提高整体施工进度,效果特别明显。……