招商局国际集装箱3#-4#泊位码头工程钢轨安装工艺探讨

2012-06-04李锐

城市建设理论研究 2012年13期

李锐

中图分类号:U213.9+2

摘要:青岛前湾招商局国际集装箱码头3#、4#泊位主体工程采用的比利时进口钢轨压板、配件开展了标准段施工工艺方法,改变了以往钢轨接头焊接工艺,革新了钢垫板调平工艺,针对钢轨安装存在的问题分析原因、制定对策,通过对策实施,提高了钢轨安装合格率。在钢轨安装过程中创新钢轨的加工、制作、安装工艺,用细节质量上的提升带动了整个工程质量的提高。

关键词:标准段施工 表面高差 调平螺栓 钢轨接头焊接

China Merchants International Container terminal Wharf Engineering3#-4# quay berth Rail installation engineering Technology discussion

lirui

NO.2 ENGINEERING COMPANY LTD.OF CCCC FIRST HARBOR ENGINEERING COMPANY LTD,Shandong,Qingdao,266071,china

Abstract:this article describes China Merchants International Container terminal Wharf Engineering of qianwan Qingdao 3#-4# quay berth, how to carry out Standard construction ,In order to slove the Belgium Rail accessories qualified rate,and how to improve the installation quality of rail accessories, Installation problems to analyze the reasons for the rail, to develop countermeasures through the implementation of countermeasures to improve the rail to install a pass rate ,through these changed the rail joint welding process, innovation in the steel plate leveling process, led to enhance the details of the quality improvement of the quality of the whole project.

Key words:Standard constructionSurface elevationRegulating boltbond weld Qualified rate

前言

青岛招商局国际集装箱码头工程是重力顺岸式码头,采用沉箱结构。工程规划建设5个10万吨级大型集装箱专用泊位,2个5万吨级多用途泊位,码头前沿水深-22m,顶面标高+5.8m。,是重力式码头的典范,也是青岛市的窗口工程。

正文

本文针对青岛前湾招商局国际集装箱码头1#、2#泊位主体工程钢轨安装测点合格率只有88.8%,既影响码头观感质量,又难以满足业主要求的现状,以“提高钢轨安装合格率、创建局精品工程”为目标,力求在细节上提高工程质量,使码头整体施工水平达到新高度。

钢轨安装工序:预留轨道槽及锚固螺栓孔、凿毛清孔、安装锚固螺栓、灌注锚固螺栓孔胶泥

安放钢垫板及调平螺栓、调平后灌注轨道槽胶泥、焊接下压板、铺设胶垫板及钢轨、钢轨调直、安装上压板、焊接钢轨接头、灌注轨道专用沥青

1、招商局国际集装箱码头工程1#-2#泊位钢轨安装技术参数现状调查,基本情况如下:

对已交工的招商局1#~2#泊位的资料进行了调查和分析,对主要不合格测点项目进行分析,经分析钢轨接头表面高差是影响装卸桥钢轨安装合格率的症结所在。……