高速铁路路基插板式金属风屏障施工技术
2012-06-04涂俊柱
涂俊柱
摘要:就武广客专新衡山站路基风插板式金属屏障工程施工技术,进行了探讨和实施,并在实际施工中取得了良好的效果,可为类似工程提供参考。
关键词:风屏障;底梁;H型钢立柱;金属单元板
Construction Technology of Subgrade-inserted Metal Air Barrier for high speed railway
TU Jun-Zhu 1
(1.No.4 Engineering Corporation Limited of China Railway 14th Bureau Group,China )
Abstract: The present paper reviewed and discussed the construction technology of subgrade-inserted metal air barrier, which was built for the new Hengshan station in the Wuhan-Guangzhou high speed railway. This technology was well performed in real construction performance and this paper provided a reference for the similar construction project.
Key words: air barrier; bottom beam; H-shaped steel column ; metal panels
1 引言
随着京津城际、武广客专等高速铁路的正式运营,高速铁路运营的安全性越来越受到大家的重视。风屏障作为减少动车侧向风的有效手段,正广泛应用于新建高速铁路上。
2 工程概况
武广客专新衡山站位于湖南省衡阳市南岳区,车站下为填方路基,路基长度约2公里,填料类别为AB组料,填筑高度大于7m。
新衡山站路基风屏障1382.3延米,其中钻孔桩2115延米,砼底梁1382.3延米,H2990型钢立柱698根,金属单元板4188块,施工时间多为联调联试期间,既有线施工,安全要求高,施工时间短且多为夜间施工,施工难度大。
3 施工流程及操作要点
施工工艺流程:
3.1 风屏障砼底梁施工
(1)根据施工图纸、施工规范和作业指导书认真编写技术交底,技术交底要具有具体性、可操作性,并对作业层认真交底。
(2)测量放线
根据图纸放出每个钻孔桩中心桩,钻孔前引出护桩。
(3)钻孔施工
钻机为履带式,可直接驶入并将钻头中心直接对位,调整钻机垂直度精准定位;定位后开始钻孔,孔深约为6m,路基为碾压合格的加筋AB组料,自稳性很好,不需要埋设护筒。钻机钻孔时要随时根据护桩校核钻机位置和垂直度。由于钻孔施工前路基基床表层已经填筑完成,为防止钻机走动和钻孔时破坏路基面,钻机施工范围内铺设5mm厚车道板保护路基面。……