水泥稳定碎石基层双层连铺施工工艺

2012-06-04王法军吕贵宾

城市建设理论研究 2012年13期
关键词:基层施工

王法军吕贵宾

中图分类号:TU74文献标识码: A 文章编号:

摘要:以前水泥稳定碎石基层传统的施工工艺是上下基层分层摊铺,既延长了施工时间,又增加了施工成本。某工程水泥稳定碎石基层采取了基层双层连铺施工,通过该项目水泥稳定碎石基层双层连铺施工,比较了双层连铺施工与传统基层分层摊铺的不同及优点。总结了双层连铺的施工流程图及施工工艺。

关键词:基层双层连铺施工工艺

Abstract: before the cement stabilized macadam base of traditional construction technology is next basic level layered paver, prolonging the time of construction, and increase the construction cost. A project of cement stabilized macadam base take the double layer paving construction, through the project of cement stabilized macadam base double layer paving construction, compared to the double layer paving construction and traditional basic layered paver and different advantages. Summary of the double layer paving construction process and construction process.

Key words: basic Double Layer Paving Construction Technology

一、工程概况国家高速公路网长春至深圳线青州至临沭(鲁苏界)公路位于山东省中部,是国家高速公路网长深公路和山东省“五纵连四横、一环绕山东”高速公路网之“纵二”东营港至临沂(鲁苏界)的组成部分,是山东省2010年交通远景规划目标和“十一五”期间重点建设项目之一。全线采用双向6车道高速公路标准建设,设计速度120公里/小时,路基设计宽度34.5米,路面结构为160mm水泥稳定风化砂底基层、 160mm+180mm水泥稳定碎石基层、150mm大粒径透水性沥青柔性基层、8mm的下面层、6mm中面层、4mmSMA-13上面层。对于基层图纸设计要求基层采用上下基层双层连铺施工工艺。

二、基层双层连铺与分层摊铺的比较

1、传统的分层摊铺需要的时间长,影响进度。

下基层摊铺完毕后需要养护至少七天,待各项指标满足要求,清理干净摊铺面后在施工上基层,养生又至少七天,一个施工段落至少需要15天的时间,严重影响进度。

2、分层摊铺上下层之间粘结质量不易保证。

水稳层为半刚性基层,第一层硬化后铺筑第二层,层间粘合性差,形成分层,易形成单层受力使薄的一层产生过大的拉应力出现开裂等现象,严重者会造成水稳层断板,影响路面的使用寿命。……