套管跟进预应力锚固技术在湖北江坪河水电站滑坡变形体加固工程中的应用
2012-06-04张晓安任红卫
张晓安任红卫
摘要::预应力锚固技术的最大特点是通过锚固措施合理地提高可利用岩体或土体的强度,在深覆盖复杂地层边坡加固锚索施工中,塌孔频繁、成孔困难直接影响工程进度及投资。湖北江坪河电站滑坡变形体加固工程采用了套管跟进预应力锚固技术成功取得了较好的效果。
关键词:滑坡变形体;深覆盖层;套管跟进法;预应力锚索
Abstract :: most prominent feature of prestressed anchor is reasonable to increase the strength of the rock or soil through the anchorage, the construction of deep cover complex formation slope reinforcement anchor cable, hole collapse frequent, difficult hole direct impact on projectprogress and investment. Hubei Jiangpinghe power station landslide deformation strengthening works of the casing follow-up of prestressed anchoring technique successfully obtained good results.
Key words: deformation landslide body; deep overburden; casing follow-up method; Prestressed Anchor
中图分类号: TV74 文献标识码:A文章编号:
1.工程概况
湖北溇水江坪河水电站右岸瓦屋台滑坡变形岩体位于江坪河水电站坝址下游约2.0km处。滑坡前该处河谷呈“V”型,两岸地形较整齐对称。河谷深切形成了高差达1000m以上的高陡斜坡,滑坡体原始地形呈上陡、中缓、下陡的形状,为斜交反向坡。
滑坡体主要由残坡积、崩积的松散的碎石粘土、崩块石夹土等覆盖层构成。高程630m以下主要为碎、块石粘土,碎、块石以灰色粉砂岩、泥灰岩为主,胶结较松散,碎、块石直径一般小于1m;高程630m以上由崩塌堆积的灰岩、少量粉砂岩块石夹残坡积的土及碎块石组成,崩块石最大直径达10m~20m。由于覆盖层厚度平均35m,常规钻孔成孔困难,采用套管跟进法进行锚索钻孔施工。
本工程2008年11月15日进场施工至2009年2月18日完工,完成无粘结预应力锚索48束,共计4320000kN.m。
锚索施工前 锚索施工后
2.施工设计
该抢险加固工程锚索设计长度为60m,锚固长度12m,轴线与水平方向的夹角为15°。锚索采用10Φ18高强度低松驰钢绞线,强度为1000KNM钢绞线,10根钢绞线组成一束,其中锚固段长12m,张拉段长48m,10根钢绞线设计拉力为1500KN。……