浅谈砂石系统生产废水处理运行维护的费用计算
2012-06-04李欣蓉周建成
李欣蓉周建成
摘要:现代水电工程砂石系统生产运行将产生大量废水,为达到国家排污要求,则必须对生产废水进行处理,处理后的清水满足砂石料冲洗回用水质要求,废水基本做到“零排放”。 该系统是环保水保的重点实施项目,也是一项新技术、新工艺,运行费用计算有多种方法,本文以糯扎渡水电站火烧寨沟砂石料加工系统生产废水处理工程运行维护为例,采用实物工程量法分析计算废水处理系统运行的费用,为类似项目的费用计算提供一种思路和参考。
关 键 词:砂石加工系统;废水处理;实物工程量法;费用
Abstract: the modern hydropower engineering sand system operation will produce the large amount of waste water, to achieve national emission requirements, it must be on production wastewater was treatment, the application of water reuse water quality requirements to meet flush, wastewater basic do zero emission. The system is the key environmental protection water conservation project implementation, and is a new technology, new technology, operation expenses have many kinds of methods, this paper to waxy firm crossing hydropower station application processing system fire village groove production wastewater treatment engineering operation and maintenance for patients, the physical quantity analysis and calculation method of wastewater treatment system operation cost, for similar project cost calculation provides a kind of mentality and reference.
中图分类号:X703 文献标识码:A文章编号:
现代水电工程砂石系统生产运行将产生大量废水,为达到国家排污要求,则必须对生产废水进行处理,处理后的清水满足砂石料冲洗回用水质要求,废水基本做到“零排放”。 该系统是环保水保的重点实施项目,也是一项新技术、新工艺,运行费用计算有多种方法,本文以糯扎渡水电站火烧寨沟砂石料加工系统生产废水处理工程运行维护为例,采用实物工程量法分析计算废水处理系统运行的费用,为类似项目的费用计算提供一种思路和参考。
1 、工程概况
糯扎渡水电站位于云南省普洱市和澜沧县交界处的澜沧江干流上,是澜沧江中下游河段规划“二库八级”的第五个梯级。糯扎渡水电站砂石料加工系统生产废水处理工程分为两处,即火烧寨沟砂石料加工系统生产废水处理系统和勘界河砂石料加工系统生产废水处理系统。……