APP下载

浅析拖拉法在钢桁梁架梁施工中的应用

2012-03-23张银松

城市建设理论研究 2012年4期
关键词:应用施工

张银松

摘要:本文以广深四线石龙北大桥中3×72m钢梁假设施工为例,介绍在中间孔为主航道,两边孔为非通航孔。施工期间不能封锁主航道,且在既有广深线旁,广深线是内地与香港地区间唯一的铁路通道,钢桁梁架设期间如何确保安全、质量,浅析钢桁梁的架设拖拉法在钢桁梁架梁施工中的应用。

关键词:拖拉法;钢桁梁;架梁;施工;应用

Abstract: Take north bridge in shilong 3 x 72 m steel beam assumption construction as the example, this paper introduces mainly in the middle hole channel, both sides for the navigation hole. During the construction can't block main channel , and in both the GuangShenXian, GuangShenXian is between mainland China and Hong Kong area the only railway channel, steel truss girders during erection how to ensure the safety, quality, according to the steel truss girders of the erection method in steel truss bridge drag whole construction of application.

Key Words: drag method; steel truss girders; frame beams; construction; application

中圖分类号:TU74文献标识码:A文章编号:

1、工程概况:

作为广深四线的重点、难点控制工程,石龙北大桥横跨东江两岸,连接石碣、石龙两大经济重镇,全桥长436.06m。大桥中心里程K67+625.56,孔跨为:5-32m后张梁+3-72m钢桁梁+2-20m后张梁。本文施工为大桥第6、7、8三跨为Lp=70.90(单跨全长72m)钢桁梁,它跨越东江北支流航道和两非通航孔;主桁高度11.50m(全高12.10m);主桁宽12.0m(全宽12.62m);下弦节间距3.545m,20个节间,21节点;上弦节间距7.09m,8个节间,9个节点;杆件最大安装重量为6.41吨,钢梁每孔重613.9吨(包括检查设备及支座);支座高度270mm;主桁杆件除端斜杆为箱型结构外,其余均为H型;纵、横梁为工字型截面;上下平联均为工字型截面;钢梁所有杆件均采用高强度螺栓联结,每孔钢梁高强度螺栓用量43973套,钢梁设置上拱度,跨中拱度69.3mm。

2、施工准备

本着精优高原则,完善施工组织,积极采用新技术、新工艺,安排精干队伍,合理配置设备,组织流水作业,合理安排工期,确保工程优质,按期完成。根据该桥的功能特点及现场实际情况,按照施工方案进行技术、测量放线、临时设施、机具设备等准备。

3、施工方案及施工工艺

本桥第6、第……

登录APP查看全文

猜你喜欢

应用施工
后浇带施工技术在房建施工中的践行探索
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
多媒体技术在小学语文教学中的应用研究
分析膜技术及其在电厂水处理中的应用
GM(1,1)白化微分优化方程预测模型建模过程应用分析
煤矿井下坑道钻机人机工程学应用分析
气体分离提纯应用变压吸附技术的分析
会计与统计的比较研究
土木工程施工实习的探讨与实践