APP下载

乌东德右岸电站24kV离相封闭母线安装工艺

2021-11-28杨家菊

河南科技 2021年16期
关键词:焊接支架

杨家菊

摘 要:乌东德右岸电站离相封闭母线主母线外壳尺寸1 600 mm/1 200 mm,额定电流大。母线洞内设备布置紧凑,主变洞低压侧母线安装高度高,母线的调整就位以及抱瓦、清扫等均为高空作业,施工难度大。因此,保证封闭母线安装质量及安装效率是封闭母线安装的控制重点。本文对乌东德右岸电站封闭母线安装工艺及质量控制进行了详细介绍。

关键词:离相;封闭母线;支架;焊接;吊装;同心度

中图分类号: TM645.11文献标识码:A文章编号:1003-5168(2021)16-0042-05

Abstract: From a lady phase enclosed bus line on the right bank of the Wu dong de shell size 1 600 mm/1 200 mm, large rated current, busbar hole equipment layout is compact, height of main transformer low voltage side bus bar installation hole is high, the adjustment of the bus in place, tile, cleaning are aerial work, such as the construction is difficult, ensure the quality of enclosed bus bar installation and the installation efficiency is the control key of enclosed bus bar installation. This paper introduces the installation technology and quality control of the closed bus in the right bank power station of Wudongde in detail.

Keywords: off-phase; closed bus; bracket; welding; lifting; concentricity

乌东德右岸水电站共安装6台单机容量为850 MW的立轴混流式水轮发电机组。离相封闭母线及附属设备的安装主要包括主回路母线(含主变低压侧△连接母线)、分支母线(含GEBS三相短接母线)、主回路电流互感器、励磁变压器、电压互感器(Potential Transformer,PT)柜、制动开关、微正压装置、设备固定支架、吊架、短路板、穿墙及穿楼板密封结构等。

离相封闭母线水平段布置在母线洞内及主变洞内。母线洞位于主厂房的下游侧,地面高程与主厂房出线层相同,并连通主厂房和主变洞室。在母线洞内,离相封闭母线通过分支母线分别与励磁变压器、PT柜、电气制动开关装置以及高压厂用变压器等连接。

1 技术参数

离相封闭母线安装技术参数,如表1所示。

2 施工条件

施工主要满足以下4个条件:①母线洞土建基础施工完成并验收合格;②发电机出口定子引出线已安装完成;③发电机断路器(Generator Circuit Breaker,GCB)上游侧母线安装,在母线洞内布置的厂用电设备及发电电压设备均未进场,GCB下游侧母线安装,在主变洞内主变压器已安装完成并验收[1];④母线已到货,开箱清点完毕。……

登录APP查看全文

猜你喜欢

焊接支架
支架≠治愈,随意停药危害大
给支架念个悬浮咒
三维多孔电磁复合支架构建与理化表征
前门外拉手支架注射模设计与制造
浅谈桥梁工程焊接质量管理的研究
CO2气体保护焊在设备制造焊接中的应用
带压堵漏技术在检修中的应用
钢结构焊接中存在问题原因分析与预防研究
铝合金构件焊接变形研究及焊接工艺优化
下肢动脉硬化闭塞症支架术后再狭窄的治疗