造船先行工法设计探讨

2021-03-24陈锌黄华锋

广东造船 2021年1期

陈锌 黄华锋

摘    要:本文阐述了船舶开展先行工法设计的条件与时机,以某船厂成功建造的挖泥船、集装箱船等产品在船舶详细设计与生产设计衔接过程中发现的问题,结合详细设计数据和具体工法优化设计案例,通过对比得出船厂开展先行工法设计有利于船舶建造精度控制、简化生产流程、提高产品完整性;并提供了船舶设计与建造工艺、工法设计有机结合的前瞻性方法参考;同时,对开展先行工法设计的局限性及解决办法进行讨论。

关键词:工法设计;详细设计;生产设计

中图分类号:U673.2                                文献标识码:A

Abstract: This paper states the conditions and timing of advance technical design. Taking the problems found in the connection between ship detailed design and production design of dredgers, container ships and other products successfully built by a shipyard as an example, combined with the detailed design data and the specific technique optimization design case, it is concluded that the shipyard's carrying out the advance technical design is beneficial to the precision control of ship construction, the simplification of production process and the improvement of product integrity, and provides a forward-looking method reference for the organic combination of ship design and construction technical design; at the same time, the limitation and solution of the advance technical design are discussed.

Key words: Shipbuilding technical design;  Detailed design;  Production design

1     前言

船舶设计分为:基本设计、详细设计、生产设计。船厂主要负责生产设计,工法设计属于生产设计的范畴。

船舶工法设计是指以船体结构为主要对象、工艺为核心,在确保设计满足规范要求、建造成本、施工质量、生产安全性的前提下,综合考虑机、电、舾各专业的协调,达到先进的设计和高效的建造技术。

对于大多数船厂,船舶的详细设计主要由设计公司负责,船厂主要负责生产设计,其中包含了工法设计。分段(总段)划分、基准线方案、建造精度方案、分段建造流程、总段建造流程、船台快速搭载等都属于工法设计内容。工法设计是在详细设计确定后开展的,我们称为后行工法设计,这个阶段工法设计的作用主要是施工流程规范化、标准化,让每个流程有法可依。

如果原设计存在影响施工效率、增加成本的地方,需要对详细设计进行优化或者改进,就需要工法设计提前在详细设计时介入,详细设计阶段介入的工法设计称为先行工法设计。……