沿空巷道注矿用无机加固复合砂浆的应用与效果分析
2020-12-23彭大鹏
彭大鹏


【摘 要】沿空巷道沿空侧巷帮(保护煤柱)是应力集中区域,在掘进期间两帮巷道压力显现明显,位移量大,巷道变形很难控制。对沿空巷道上帮注矿用无机加固复合砂浆就是在巷道掘进期间,对巷道沿空侧进行有效注浆加固,通过对巷道两帮整体位移的观测,注浆效果对控制巷道位移有较好的效果。
【Abstract】The gob-side roadside of gob-side roadway(protective coal pillar) is the stress concentration area. During the drilling period, the pressure of the two roadsides of roadway appears obviously, the displacement is large, and the deformation of roadway is difficult to control. Grouting with mine-used inorganic reinforced composite mortar into the upper roadside of gob-side roadway is to carry out effective grouting reinforcement on the gob-side of the roadway during the roadway drilling. Through the observation of the overall displacement of the two roadsides of the roadway, the grouting effect has a good effect on controlling the roadway displacement.
【关键词】沿空巷道;矿用无机加固复合砂浆;位移量
【Keywords】gob-side roadway; mine-used inorganic reinforced composite mortar; displacement
【中图分类号】TD822.3;TD353 【文献标志码】A 【文章编号】1673-1069(2020)07-0178-02
1 引言
谢桥煤矿11518轨道顺槽为该矿第一个柴油单轨吊使用头面,因受11418工作面回采影响,巷道上帮位移量较大。为保证掘进期间的单轨吊使用,且保证后期回采巷道断面,故在巷道掘进至420m处开始采用注矿用无机加固复合砂浆的方法对巷道上帮进行加固。
2 地质情况
11518轨道顺槽位于矿井一水平东一采区,工作面底板标高-605.1~-616.2m,巷道设计长度1850m,宽度5.5m。轨道顺槽11518上顺槽西起11518轨道顺槽车场,东至11518切眼。工作面轨道顺槽与11418运输顺槽、13318运顺槽阶段煤柱分别为6.8~15.7m、7.0m。上覆11-2煤层未回采,下伏6煤层11316、21116工作面已回采完毕,11416工作面已停采(2018年9月),停采时间较短。上阶段11418、13318工作面已回采完毕,11416顶抽巷位于本巷以南,巷顶距8煤底板法线0~32.8m。-610m新东二B组轨道石门、-610m新东二B组回风石门及1#联巷位于工作面上方,东一B8煤层底板皮带下山位于工作面下方,与本巷净垛分别为11.5m、9.9m、10.6m、10.2m。
8煤整体赋存稳定,煤层总厚1.2~4.1m,平均3.0m。黑色,金屬-油脂光泽,以亮煤为主,少量暗煤,亮煤块状,垂直解理发育,局部含1层泥岩夹矸,煤层结构简单。……